# Akashi Data Center (Astana)

AI data center campus tracked on DEPLOY: announced-vs-energized capacity, each figure dated and sourced.

- **Canonical ID:** 025b7841-ad1f-47b2-ac65-6ffaa31b1c1a
- **Type:** AI data center campus
- **Operator / developer:** [Freedom Holding](/companies/freedom-holding.md)
- **Location:** Astana, Kazakhstan
- **Lifecycle state:** under_construction
- **Announced capacity (GW):** 0.1
- **Energized capacity (GW):** 0.04834
- **Announced-to-energized gap (GW):** 0.052

## Capacity ledger (append-only, dated, sourced)

- announced: 0.1 GW · reported · as of 2025-06-18 · https://astanatimes.com/2025/06/kazakhstan-to-build-central-asias-first-tier-iv-data-center/
- energized: 0.04834 GW · reported · as of 2026-08-30 · https://akashi.cloud/about/

## Parties

- Freedom Holding (operator): https://registry.deploy.report/companies/freedom-holding

## Common questions


**What is Akashi Data Center (Astana)?**

Akashi Data Center (Astana) is an AI data center campus tracked on the DEPLOY registry, located in Astana, Kazakhstan. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.

**How much power will Akashi Data Center (Astana) use?**

Akashi Data Center (Astana) has 0.10 GW of announced capacity on the DEPLOY registry, of which 0.05 GW is recorded as energized, an announced-to-energized gap of 0.05 GW. Each figure is individually dated and sourced.

**Who is building Akashi Data Center (Astana)?**

Freedom Holding is recorded as a party to Akashi Data Center (Astana) on the DEPLOY registry. The full party list, with each role, is on the record.

**Is Akashi Data Center (Astana) operating yet?**

As of the most recent verification on the DEPLOY registry, Akashi Data Center (Astana) is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.

**How verified is the data on Akashi Data Center (Astana)?**

A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

## Sources

- About — Akashi Data Center: https://akashi.cloud/about/
- Kazakhstan to Build Central Asia's First Tier IV Data Center: https://astanatimes.com/2025/06/kazakhstan-to-build-central-asias-first-tier-iv-data-center/
- Freedom Holding to Build $2B Sovereign AI Hub in Kazakhstan Powered by NVIDIA: https://ir.freedomholdingcorp.com/press-releases/detail/86/freedom-holding-corp-to-build-2b-sovereign-ai-hub-in

Canonical: https://registry.deploy.report/datacenters/freedom-akashi-data-center-astana
JSON: https://registry.deploy.report/v1/datacenters/freedom-akashi-data-center-astana