_Incident · Property damage_

# Fire damages two buildings at Bitdeer Massillon, Ohio data center construction site

Canonical ID: `04fa129b-6e90-47ed-93dc-4613029ffec0`

- **Occurred:** 2025-11-11
- **Kind:** `property_damage`
- **Status (derived):** active
- **Company:** [Bitdeer Technologies](/companies/bitdeer-technologies.md) (id: `3fd17461-d5be-49a7-88dd-0a88b278eda2`)

On November 11, 2025, a fire broke out at Bitdeer's under-construction data center in Massillon, Ohio, damaging two of the 26 buildings in the complex. No personal injuries were reported. The Massillon Fire Department found no signs of arson. Bitdeer reported that reconstruction of the two fire-damaged buildings (26MW) was underway and expected to be completed by Q3 2026, with a significant portion of reconstruction costs recovered through the supplier's insurance coverage.

## Sources (1)

1. **Bitdeer IR** · https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-reports-fire-incident-massillon-development-site · 2025-11-11

## Status history

- **active** · 2026-08-18 · agent:recon

## Common questions

### What happened in Fire damages two buildings at Bitdeer Massillon, Ohio data center construction site?

On November 11, 2025, a fire broke out at Bitdeer's under-construction data center in Massillon, Ohio, damaging two of the 26 buildings in the complex. No personal injuries were reported. The Massillon Fire Department found no signs of arson. Bitdeer reported that reconstruction of the two fire-damaged buildings (26MW) was underway and expected to be completed by Q3 2026, with a significant portion of reconstruction costs recovered through the supplier's insurance coverage.

### When did this incident occur?

The incident is recorded as occurring on November 11, 2025 on the DEPLOY registry. The date reflects the underlying real-world event, not the registry record's creation date.

### Who was involved in Fire damages two buildings at Bitdeer Massillon, Ohio data center construction site?

The incident is recorded as involving Bitdeer Technologies on the DEPLOY registry. No specific robot model is linked to this incident in the registry.

### Has anyone responded to Fire damages two buildings at Bitdeer Massillon, Ohio data center construction site?

No responses to this incident are recorded on the DEPLOY registry. Operators, manufacturers, or affected parties can submit responses to the editorial team; absence is not a guarantee no response was issued.

### What is the current status of Fire damages two buildings at Bitdeer Massillon, Ohio data center construction site?

This incident is an active record on the DEPLOY registry; no retraction or correction has been issued.


_API: GET /v1/incidents/04fa129b-6e90-47ed-93dc-4613029ffec0 · sources: /v1/incidents/04fa129b-6e90-47ed-93dc-4613029ffec0/sources · responses: /v1/incidents/04fa129b-6e90-47ed-93dc-4613029ffec0/responses · status: /v1/incidents/04fa129b-6e90-47ed-93dc-4613029ffec0/status · canonical URL: /incidents/bitdeer-massillon-fire-2025-11_