{"id":"49044b3a-b534-4134-b8b4-461e0eb98bf2","slug":"amazon-project-rainier-indiana","name":"Amazon Project Rainier Data Center (New Carlisle)","aliases":[],"locationId":"c047df0e-c90d-414c-a6db-cc46828fa89f","lat":41.6902,"lng":-86.4687,"locationPrecision":"exact","landStatus":"private","lifecycleState":"partially_energized","powerSourceMix":"grid","interconnectionQueueStatus":"Grid connected, utility build in progress: AEP is building two new 345 kV delivery substations, Larrison Drive and New Prairie, plus fault-duty upgrades at the existing Olive station, a transmission package of about $185 million targeting roughly 1.1 GW of service by December 2026. Indiana Michigan Power holds a separate authorisation of about $68 million for its own New Carlisle 345 kV station. Full build-out is planned at 2.2 GW.","interconnectionQueueId":null,"expectedEnergizationDate":"2027-01-01T00:00:00.000Z","expectedEnergizationPrecision":"half","expectedEnergizationMilestone":"next_phase","dedicatedSubstation":null,"gridOperator":"PJM","waterSourceNotes":"Uses free-air cooling about 90% of the year, switching to evaporative (water) cooling only when ambient temperature exceeds ~85F; cooling water is drawn from the New Carlisle aquifer, with Phase 1 permitted at ~1.6M gal/day and Amazon stating water is used in under 2% of hours annually.","servingUtility":null,"acreage":null,"totalBuildingSqft":null,"streetAddress":null,"notes":"Project Rainier is AWS's ~$11B New Carlisle campus dedicated to training and serving Anthropic's Claude models on Amazon's own Trainium chips; Amazon declared it operational in October 2025 with ~500,000 Trainium2 chips running. As of March 2026 Buildings 1-16 were operational (~910 MW IT power per Epoch), with the full site planned for 30 buildings and >2.2 GW; Anthropic targets roughly 1 GW of Trainium online by end of 2026. Power is grid-supplied by Indiana Michigan Power (AEP) within PJM. This is the most-energized of the four: a real operating figure exists, well below the 2.2 GW announced ceiling.","keyFacts":[{"label":"Operator / tenant","value":"AWS Project Rainier, built with Anthropic to train and serve Claude"},{"label":"Chips (company-claimed)","value":"Nearly 500,000 Trainium2 chips; Anthropic on 1M+ by end of 2025"},{"label":"Compute (company-claimed)","value":"Over five times the compute of Anthropic's prior training"},{"label":"Cooling (company-claimed)","value":"Outside-air cooling; no cooling water Oct-Mar"},{"label":"Campus (reported, Oct 2025)","value":"About $11B; about 1,200 acres in New Carlisle; seven buildings online; over 2.2 GW eventual"},{"label":"Scope","value":"Rainier spans several US sites; this record covers New Carlisle, St. Joseph County"}],"reviewStatus":"reviewed","sources":[{"url":"https://www.cnbc.com/2025/10/29/amazon-opens-11-billion-ai-data-center-project-rainier-in-indiana.html","title":"Amazon opens $11 billion AI data center Project Rainier in Indiana","sourceName":"CNBC"},{"url":"https://epoch.ai/data/ai-data-centers/directory/anthropic-amazon-new-carlisle","title":"Anthropic-Amazon New Carlisle | AI Data Centers","sourceName":"Epoch AI"},{"url":"https://www.blackridgeresearch.com/project-profiles/aws-project-rainier-new-carlisle-indiana-usa-data-center-supercluster-cost-contractors-timeline-latest-updates","title":"AWS Project Rainier, Indiana: Latest Updates (2026)","sourceName":"Blackridge Research"},{"url":"https://measuredai.substack.com/p/aws-new-carlisle-data-center-campus","title":"AWS New Carlisle Data Center Campus: Project Rainier","sourceName":"MeasuredAI"},{"url":"https://wsbt.com/news/local/only-on-22-amazon-leader-answers-questions-surrounding-incoming-data-center-aws-amazon-web-services-water-electricity-aquifer-power-grid-new-carlisle-st-joseph-county-indiana","title":"Amazon leader answers questions surrounding incoming New Carlisle data center","sourceName":"WSBT"},{"url":"https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster","title":"AWS activates Project Rainier (Trainium2 / Anthropic)","publisher":"Amazon / AWS"},{"url":"https://www.neoteo.com/en/awss-indiana-data-center-was-partly-operational-as-construction-continued","title":"AWS's Indiana data center was partly operational as construction continued","sourceName":"Neoteo (relaying South Bend Tribune 2026-11-09)","publishedAt":"2026-11-12"}],"reviewNote":null,"createdAt":"2026-08-17T18:11:39.758Z","updatedAt":"2026-11-18T03:28:22.442Z","location":{"id":"c047df0e-c90d-414c-a6db-cc46828fa89f","name":"New Carlisle","slug":"new-carlisle-indiana","kind":"city","parentLocationId":"7fda7dfe-fa16-478b-b456-7a3f45a33844","region":"Indiana","lat":41.7,"lng":-86.5,"reviewStatus":"reviewed","aliases":[],"collisionRisk":"high","reviewNote":null,"createdAt":"2026-08-17T18:11:39.386Z","updatedAt":"2026-08-21T03:20:12.226Z"},"parties":[{"id":"e25c784f-3ad6-46e6-a789-065355c71b75","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":null,"externalName":"Indiana Michigan Power (AEP)","role":"utility","structureNotes":"Grid supply and high-voltage interconnection.","createdAt":"2026-08-17T18:11:47.611Z","company":null},{"id":"337ca623-de99-4aef-b2c1-32655c790e61","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":null,"externalName":"PJM","role":"grid_operator","structureNotes":"I&M operates within PJM Interconnection.","createdAt":"2026-08-17T18:11:48.361Z","company":null},{"id":"6e61c15d-3764-49bb-954a-8210ca8c46ba","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":"5fd474ba-cc8c-404b-8655-0b951c57e9d5","externalName":"Anthropic","role":"tenant","structureNotes":"Primary tenant; trains and serves Claude models on the cluster.","createdAt":"2026-08-17T18:11:45.355Z","company":{"id":"5fd474ba-cc8c-404b-8655-0b951c57e9d5","name":"Anthropic","slug":"anthropic"}},{"id":"d62fcd37-2f78-41ab-9a50-95d904ae1f0b","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","externalName":"Amazon Web Services","role":"developer","structureNotes":"Owner-operator of the ~1,200-acre New Carlisle campus.","createdAt":"2026-08-17T18:11:44.604Z","company":{"id":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","name":"Amazon","slug":"amazon"}},{"id":"142a1157-db05-414e-9a97-7c5738bc63cc","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","externalName":"AWS Annapurna Labs (Trainium2/Trainium3)","role":"chip_supplier","structureNotes":"Amazon's in-house AI accelerators; ~500k Trainium2 chips deployed.","createdAt":"2026-08-17T18:11:46.113Z","company":{"id":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","name":"Amazon","slug":"amazon"}},{"id":"946e6005-b0fa-42a0-811e-4763e95d39bf","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","companyId":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","externalName":"Amazon","role":"investor","structureNotes":"Strategic investor in Anthropic in addition to infrastructure provider.","createdAt":"2026-08-17T18:11:46.855Z","company":{"id":"b9b40dbf-7909-4d29-9bd9-e23f21bf06f9","name":"Amazon","slug":"amazon"}}],"capacityClaims":[{"id":"8e5a7b13-016e-4b9f-91be-f668668a1a49","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","series":"announced","valueGw":2.2,"asOf":"2025-10-29T00:00:00.000Z","sourceUrl":"https://www.cnbc.com/2025/10/29/amazon-opens-11-billion-ai-data-center-project-rainier-in-indiana.html","sourceType":"journalist_report","evidenceTier":"claimed","supersedesId":null,"note":"Full site to span 30 buildings and draw >2.2 GW.","createdAt":"2026-08-17T18:11:40.533Z"},{"id":"fb49a3b4-db56-481d-9a1b-4b1281a9fca6","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","series":"energized","valueGw":0.91,"asOf":"2026-03-23T00:00:00.000Z","sourceUrl":"https://epoch.ai/data/ai-data-centers/directory/anthropic-amazon-new-carlisle","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":"Buildings 1-16 operational, ~910 MW IT power; ~500k Trainium2 chips running since Oct 2025.","createdAt":"2026-08-17T18:11:41.369Z"},{"id":"abb11870-8f79-4edf-a520-b14d8797bb42","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","series":"under_construction","valueGw":1.925,"asOf":"2028-01-01T00:00:00.000Z","sourceUrl":"https://epoch.ai/data/ai-data-centers/directory/anthropic-amazon-new-carlisle","sourceType":"journalist_report","evidenceTier":"claimed","supersedesId":null,"note":"Projected ~1,925 MW IT power by Q1 2028 as remaining buildings complete; Anthropic targets ~1 GW Trainium online by end 2026.","createdAt":"2026-08-17T18:11:42.184Z"}],"financialClaims":[{"id":"81686aff-a0f3-4f0b-97c0-853530a2c9cf","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","kind":"transmission_build","label":"AEP transmission package serving the campus","valueUsd":"185000000","capUsd":null,"conditions":"Two new 345 kV delivery substations (Larrison Drive, New Prairie) plus fault-duty upgrades at Olive, targeting about 1.1 GW of service by December 2026. Indiana Michigan Power holds a separate ~$68m authorisation for its own New Carlisle 345 kV station.","asOf":"2026-04-01T00:00:00.000Z","sourceUrl":"https://measuredai.substack.com/p/aws-new-carlisle-data-center-campus","sourceType":"journalist_report","evidenceTier":"reported","createdAt":"2026-08-28T18:24:52.381Z"},{"id":"5be181f6-0d71-4f21-82f3-986d160ce246","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","kind":"capex","label":"Amazon Project Rainier investment (announced)","valueUsd":"11000000000","capUsd":null,"conditions":"Announced at Oct 2025 opening; Epoch estimates ~$34.5B deployed to date, ~$72.9B at full buildout.","asOf":"2025-10-29T00:00:00.000Z","sourceUrl":"https://www.cnbc.com/2025/10/29/amazon-opens-11-billion-ai-data-center-project-rainier-in-indiana.html","sourceType":"journalist_report","evidenceTier":"claimed","createdAt":"2026-08-17T18:11:43.090Z"},{"id":"f3b93346-b76d-4761-939e-b3046e18f4b4","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","kind":"guarantee","label":"Anthropic 10-year compute commitment","valueUsd":"100000000000","capUsd":null,"conditions":"Anthropic to spend >$100B on compute over 10 years and reserve up to 5 GW of Trainium capacity.","asOf":"2025-10-29T00:00:00.000Z","sourceUrl":"https://measuredai.substack.com/p/aws-new-carlisle-data-center-campus","sourceType":"journalist_report","evidenceTier":"claimed","createdAt":"2026-08-17T18:11:43.845Z"}],"metricClaims":[{"id":"cb1ed364-fe0d-4035-a4d1-c3f484e03a58","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","metricType":"gpu_count","valueNumeric":500000,"valueText":"500,000 Trainium2","unit":null,"grantingJurisdiction":null,"asOf":"2026-01-01T00:00:00.000Z","sourceUrl":"https://www.aboutamazon.com/news/aws/aws-project-rainier-data-center-anthropic","sourceType":"press","evidenceTier":"verified","supersedesId":null,"note":null,"createdAt":"2026-08-18T21:53:38.531Z"}],"powerProjects":[{"id":"fc2e3c2a-3967-4183-9d89-7f7790197cc9","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","name":"Indiana Michigan Power (AEP) grid supply","type":"grid_ppa","capacityGw":2.2,"lifecycleState":"under_construction","sourceUrl":"https://measuredai.substack.com/p/aws-new-carlisle-data-center-campus","evidenceTier":"reported","note":"I&M (AEP subsidiary) partnered with AWS to deliver high-voltage infrastructure; grid-supplied within PJM.","createdAt":"2026-08-17T18:11:42.718Z"}],"permits":[{"id":"a96669f0-2b70-497c-995c-faee27461846","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Significant source modification (4 more emergency generators)","number":"141-48867-00642","applicant":"Amazon Data Services, Inc.","status":"active","filedDate":null,"decidedDate":"2025-08-22T00:00:00.000Z","docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/48867f.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:13.359Z","updatedAt":"2026-11-18T02:56:13.359Z"},{"id":"25949efb-5715-4ab8-bb11-5af7570d4d57","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Significant Part 70 permit modification (4 more emergency generators)","number":"141-48888-00642","applicant":"Amazon Data Services, Inc.","status":"active","filedDate":null,"decidedDate":"2025-09-12T00:00:00.000Z","docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/48888f.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:13.745Z","updatedAt":"2026-11-18T02:56:13.745Z"},{"id":"af4b677b-d7e1-4f3e-b473-1355f3543674","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Significant Part 70 permit modification (2 new generators, existing generator changes)","number":"141-50312-00650","applicant":"Amazon Data Services, Inc.","status":"active","filedDate":null,"decidedDate":"2026-10-15T00:00:00.000Z","docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/50312f.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:14.117Z","updatedAt":"2026-11-18T02:56:14.117Z"},{"id":"6c6af930-7d35-45fe-bf49-1af5a47ec0a7","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Significant source modification (new building with emergency generators), draft","number":"141-50362-00650","applicant":"Amazon Data Services, Inc.","status":"pending","filedDate":null,"decidedDate":null,"docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/50375d.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:14.416Z","updatedAt":"2026-11-18T02:56:14.416Z"},{"id":"54bdce94-247e-45a3-8312-03e384c7bb1a","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Significant Part 70 permit modification (new building with emergency generators), draft","number":"141-50375-00650","applicant":"Amazon Data Services, Inc.","status":"pending","filedDate":null,"decidedDate":null,"docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/50375d.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:14.787Z","updatedAt":"2026-11-18T02:56:14.787Z"},{"id":"41d38822-e2d8-4b14-84a3-e979f203dfb0","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"New source construction + Part 70 operating permit (emergency generators)","number":"T141-47750-00642","applicant":"Amazon Data Services, Inc.","status":"active","filedDate":null,"decidedDate":"2025-01-28T00:00:00.000Z","docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/47750f.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:15.165Z","updatedAt":"2026-11-18T02:56:15.165Z"},{"id":"b8d76f3b-cf91-4056-af12-f75c05cf701d","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"air","permitType":"Part 70 operating permit, second plant (31100 State Road 2)","number":"T141-48298-00650","applicant":"Amazon Data Services, Inc.","status":"active","filedDate":null,"decidedDate":"2025-05-01T00:00:00.000Z","docket":null,"regulatedEntityId":null,"sourceUrl":"https://permits.air.idem.in.gov/48298f.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:15.463Z","updatedAt":"2026-11-18T02:56:15.463Z"},{"id":"e4075012-b69b-4a91-b94a-98129a813f8a","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","agency":"IDEM","jurisdiction":"Indiana","kind":"other","permitType":"Section 401 water quality certification (ditch and wetland impacts)","number":"2025-78-71-ENH-WQC-2","applicant":"Amazon Data Services, Inc.","status":"pending","filedDate":"2026-05-13T00:00:00.000Z","decidedDate":null,"docket":null,"regulatedEntityId":null,"sourceUrl":"https://www.in.gov/idem/files/notice_20260612_401_2025-78-71-enh-wqc-2.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:15.881Z","updatedAt":"2026-11-18T02:56:15.881Z"}],"facilities":[],"incidents":[],"events":[{"id":"042a1f81-dbc8-44d0-a50a-8796f5209954","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"air_facility_recorded","series":"IN0000001814100642","oldValue":null,"newValue":"Operating|Major Emissions|04/15/2026|No High Priority Violation","claimId":null,"detail":"EPA's Clean Air Act records list AMAZON DATA SERVICES INCORPORATED (31100 Edison Road, New Carlisle, IN) as operating, a major emissions source. Its most recent Clean Air Act violation on file is dated April 15, 2026. Source: EPA ECHO facility IN0000001814100642.","occurredAt":"2026-11-18T18:44:28.708Z","createdAt":"2026-11-18T18:44:28.708Z"},{"id":"92a3f53a-c8d8-4231-b6aa-2e589d32dc7e","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"air_facility_recorded","series":"IN0000001814100650","oldValue":null,"newValue":"Operating|Major Emissions|04/15/2026|No High Priority Violation","claimId":null,"detail":"EPA's Clean Air Act records list AMAZON DATA SERVICES INCORPORATED (31100 Sr 2, New Carlisle, IN) as operating, a major emissions source. Its most recent Clean Air Act violation on file is dated April 15, 2026. Source: EPA ECHO facility IN0000001814100650.","occurredAt":"2026-11-18T18:44:28.708Z","createdAt":"2026-11-18T18:44:28.708Z"},{"id":"8ca331d7-acd3-4e4a-9b10-0c7ff5fa57e4","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"energization_date_changed","series":null,"oldValue":null,"newValue":"2027-01-01|half","claimId":null,"detail":"intake proposal ffd19611-9e83-4acd-8f8e-37637df60184","occurredAt":"2026-11-18T03:28:23.043Z","createdAt":"2026-11-18T03:28:23.043Z"},{"id":"f239e49d-c51f-4b86-9ded-c4bd7552845f","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 2025-78-71-ENH-WQC-2: pending","claimId":null,"detail":"Section 401 water quality certification (ditch and wetland impacts) 2025-78-71-ENH-WQC-2 recorded from https://www.in.gov/idem/files/notice_20260612_401_2025-78-71-enh-wqc-2.pdf","occurredAt":"2026-11-18T02:56:16.026Z","createdAt":"2026-11-18T02:56:16.026Z"},{"id":"04c5ee11-c87c-4cdc-add2-cea37c1e70fd","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM T141-48298-00650: active","claimId":null,"detail":"Part 70 operating permit, second plant (31100 State Road 2) T141-48298-00650 recorded from https://permits.air.idem.in.gov/48298f.pdf","occurredAt":"2026-11-18T02:56:15.689Z","createdAt":"2026-11-18T02:56:15.689Z"},{"id":"37c35e19-ee54-45dc-ac82-191933b8316b","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM T141-47750-00642: active","claimId":null,"detail":"New source construction + Part 70 operating permit (emergency generators) T141-47750-00642 recorded from https://permits.air.idem.in.gov/47750f.pdf","occurredAt":"2026-11-18T02:56:15.316Z","createdAt":"2026-11-18T02:56:15.316Z"},{"id":"7c8b87b5-b64d-47f0-a28d-3025b57da034","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 141-50375-00650: pending","claimId":null,"detail":"Significant Part 70 permit modification (new building with emergency generators), draft 141-50375-00650 recorded from https://permits.air.idem.in.gov/50375d.pdf","occurredAt":"2026-11-18T02:56:14.933Z","createdAt":"2026-11-18T02:56:14.933Z"},{"id":"32fd7888-ef50-4a07-93bd-5aeb2a0b0399","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 141-50362-00650: pending","claimId":null,"detail":"Significant source modification (new building with emergency generators), draft 141-50362-00650 recorded from https://permits.air.idem.in.gov/50375d.pdf","occurredAt":"2026-11-18T02:56:14.642Z","createdAt":"2026-11-18T02:56:14.642Z"},{"id":"61fb5dd0-38a1-44b5-b04e-47fe8dd5e742","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 141-50312-00650: active","claimId":null,"detail":"Significant Part 70 permit modification (2 new generators, existing generator changes) 141-50312-00650 recorded from https://permits.air.idem.in.gov/50312f.pdf","occurredAt":"2026-11-18T02:56:14.269Z","createdAt":"2026-11-18T02:56:14.269Z"},{"id":"a43fecee-7b50-4989-a11c-75e1c46a0edc","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 141-48888-00642: active","claimId":null,"detail":"Significant Part 70 permit modification (4 more emergency generators) 141-48888-00642 recorded from https://permits.air.idem.in.gov/48888f.pdf","occurredAt":"2026-11-18T02:56:13.895Z","createdAt":"2026-11-18T02:56:13.895Z"},{"id":"168fc908-8917-417b-8906-330bb39220d4","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"IDEM 141-48867-00642: active","claimId":null,"detail":"Significant source modification (4 more emergency generators) 141-48867-00642 recorded from https://permits.air.idem.in.gov/48867f.pdf","occurredAt":"2026-11-18T02:56:13.592Z","createdAt":"2026-11-18T02:56:13.592Z"},{"id":"6e293768-e0df-454b-9508-5ea94c375041","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"transmission_build: AEP transmission package serving the campus","occurredAt":"2026-08-28T20:25:21.809Z","createdAt":"2026-08-28T20:25:21.809Z"},{"id":"a31e2b51-2a1c-4492-b083-6709b302c003","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"transmission_build: AEP transmission package serving the campus","occurredAt":"2026-08-28T18:24:52.776Z","createdAt":"2026-08-28T18:24:52.776Z"},{"id":"8e3c9396-f2de-4c75-9f89-f6e491659023","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"grid_operator: PJM","occurredAt":"2026-08-17T18:11:48.739Z","createdAt":"2026-08-17T18:11:48.739Z"},{"id":"b2f6b3c6-cfe6-4b0a-856e-5c84641441a1","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"utility: Indiana Michigan Power (AEP)","occurredAt":"2026-08-17T18:11:47.988Z","createdAt":"2026-08-17T18:11:47.988Z"},{"id":"7326e762-8e41-4558-94dd-d69d2482efb6","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"investor: Amazon","occurredAt":"2026-08-17T18:11:47.233Z","createdAt":"2026-08-17T18:11:47.233Z"},{"id":"cc065bb1-e21b-4128-a843-6cfa7c3bf0f1","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"chip_supplier: AWS Annapurna Labs (Trainium2/Trainium3)","occurredAt":"2026-08-17T18:11:46.488Z","createdAt":"2026-08-17T18:11:46.488Z"},{"id":"b5c75389-c629-49a7-a77c-870a6d6ab38a","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"tenant: Anthropic","occurredAt":"2026-08-17T18:11:45.735Z","createdAt":"2026-08-17T18:11:45.735Z"},{"id":"f3790b6e-cbd8-4044-bf28-025e643626f4","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: Amazon Web Services","occurredAt":"2026-08-17T18:11:44.985Z","createdAt":"2026-08-17T18:11:44.985Z"},{"id":"3e70e135-baab-4c2a-a1d1-ad561f76fe2c","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"guarantee: Anthropic 10-year compute commitment","occurredAt":"2026-08-17T18:11:44.228Z","createdAt":"2026-08-17T18:11:44.228Z"},{"id":"0183f300-4f27-4b85-9e2d-bc681be0d0db","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"capex: Amazon Project Rainier investment (announced)","occurredAt":"2026-08-17T18:11:43.465Z","createdAt":"2026-08-17T18:11:43.465Z"},{"id":"1ab73d26-ece3-46ca-8e82-d21720843b2e","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"capacity_changed","series":"under_construction","oldValue":null,"newValue":"1.925","claimId":"abb11870-8f79-4edf-a520-b14d8797bb42","detail":null,"occurredAt":"2026-08-17T18:11:42.489Z","createdAt":"2026-08-17T18:11:42.489Z"},{"id":"8b153072-9545-45dc-be4f-b997ba495c9b","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"claim_recorded","series":"under_construction","oldValue":null,"newValue":"1.925","claimId":"abb11870-8f79-4edf-a520-b14d8797bb42","detail":"claimed · journalist_report","occurredAt":"2026-08-17T18:11:42.336Z","createdAt":"2026-08-17T18:11:42.336Z"},{"id":"bd2bb315-1f7e-4e47-8346-2e397da6800c","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"capacity_changed","series":"energized","oldValue":null,"newValue":"0.91","claimId":"fb49a3b4-db56-481d-9a1b-4b1281a9fca6","detail":null,"occurredAt":"2026-08-17T18:11:41.668Z","createdAt":"2026-08-17T18:11:41.668Z"},{"id":"765d8ba1-e87f-48f0-9f80-11580d5c8f7e","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"claim_recorded","series":"energized","oldValue":null,"newValue":"0.91","claimId":"fb49a3b4-db56-481d-9a1b-4b1281a9fca6","detail":"reported · journalist_report","occurredAt":"2026-08-17T18:11:41.520Z","createdAt":"2026-08-17T18:11:41.520Z"},{"id":"447677df-1294-4e28-b0c8-ed090e9df6da","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"capacity_changed","series":"announced","oldValue":null,"newValue":"2.2","claimId":"8e5a7b13-016e-4b9f-91be-f668668a1a49","detail":null,"occurredAt":"2026-08-17T18:11:40.838Z","createdAt":"2026-08-17T18:11:40.838Z"},{"id":"c6e9ff3c-cac1-487d-a561-00f6ec790af0","dataCenterId":"49044b3a-b534-4134-b8b4-461e0eb98bf2","eventType":"claim_recorded","series":"announced","oldValue":null,"newValue":"2.2","claimId":"8e5a7b13-016e-4b9f-91be-f668668a1a49","detail":"claimed · journalist_report","occurredAt":"2026-08-17T18:11:40.689Z","createdAt":"2026-08-17T18:11:40.689Z"}],"capacity_picture":{"announced_gw":2.2,"contracted_gw":null,"under_construction_gw":1.925,"energized_gw":0.91,"announced_minus_energized_gw":1.29,"by_series":{"announced":{"valueGw":2.2,"asOf":"2025-10-29T00:00:00.000Z","evidenceTier":"claimed","sourceUrl":"https://www.cnbc.com/2025/10/29/amazon-opens-11-billion-ai-data-center-project-rainier-in-indiana.html"},"contracted":null,"under_construction":{"valueGw":1.925,"asOf":"2028-01-01T00:00:00.000Z","evidenceTier":"claimed","sourceUrl":"https://epoch.ai/data/ai-data-centers/directory/anthropic-amazon-new-carlisle"},"energized":{"valueGw":0.91,"asOf":"2026-03-23T00:00:00.000Z","evidenceTier":"reported","sourceUrl":"https://epoch.ai/data/ai-data-centers/directory/anthropic-amazon-new-carlisle"}}},"jsonLd":{"@context":"https://schema.org","@type":"Place","name":"Amazon Project Rainier Data Center (New Carlisle)","url":"https://registry.deploy.report/datacenters/amazon-project-rainier-indiana","geo":{"@type":"GeoCoordinates","latitude":41.6902,"longitude":-86.4687},"address":{"@type":"PostalAddress","addressLocality":"New Carlisle"}}}