{"id":"4c5d91e2-9598-4b3c-9128-702828bf4251","slug":"stargate-dona-ana-county-new-mexico","name":"Stargate Doña Ana County / Project Jupiter (New Mexico)","aliases":["Stargate Dona Ana","Dona Ana County site","Stargate New Mexico"],"locationId":"426e17fd-34c9-4de4-a2c4-c6a9d933fc9b","lat":31.9,"lng":-106.65,"locationPrecision":"city","landStatus":"private","lifecycleState":"under_construction","powerSourceMix":"behind_the_meter_gas","interconnectionQueueStatus":null,"interconnectionQueueId":null,"expectedEnergizationDate":"2026-07-01T00:00:00.000Z","expectedEnergizationPrecision":"half","expectedEnergizationMilestone":"first_power","dedicatedSubstation":null,"gridOperator":"WECC","waterSourceNotes":"Closed-loop cooling; proposed domestic water use ~20,000 gallons/day; on-site microgrid targeting net-zero emissions by 2045.","servingUtility":null,"acreage":1400,"totalBuildingSqft":null,"streetAddress":null,"notes":"An Oracle-led Stargate site in Doña Ana County, New Mexico, developed by STACK Infrastructure under the name Project Jupiter (four large buildings). Epoch AI's April 2026 tracker reports foundation work underway with satellite imagery, a planned ~2.2 GW, and power from two on-site natural gas microgrids designed to limit local-grid impact. The site sits in the WECC region (not ERCOT/PJM/MISO/SPP). No energized capacity reported yet.","keyFacts":[{"label":"Also known as","value":"Project Jupiter"},{"label":"Location","value":"Doña Ana County, New Mexico (Santa Teresa area)"},{"label":"Developer","value":"STACK Infrastructure (Oracle-led)"},{"label":"Lifecycle (reported)","value":"Under construction; foundation work seen in satellite imagery"},{"label":"Planned capacity (reported)","value":"About 2.2 GW; part of about 5.5 GW across three Oracle-led sites"},{"label":"Cooling","value":"Closed-loop; about 20,000 gal/day domestic water proposed"},{"label":"On-site power","value":"Two natural-gas microgrids; net-zero target by 2045"},{"label":"First GW target","value":"H2 2026; initial operations Q4 2026"},{"label":"Incentive","value":"Industrial revenue bond approved"},{"label":"Utility","value":"El Paso Electric"},{"label":"Force majeure (reported, Sep 2026)","value":"Oracle sent a force majeure notice on payment timing; Oracle says schedule unchanged."},{"label":"Delay (reported, Sep 2026)","value":"About one-year delay reported; Blue Owl holds about $3B of equity"},{"label":"Open issues (reported, Oct 2026)","value":"Gas supply, air permit and land access unresolved; pipeline in service Feb 1 2027."},{"label":"Renewable energy RFP (company-stated, Sep 2026)","value":"Oracle seeks proposals for 2 GW of new New Mexico solar, wind and geothermal deliverable 2027 to 2031, toward 100% carbon-free energy matching for the campus by 2031."},{"label":"IT capacity","value":"Not disclosed"},{"label":"Program","value":"Part of the Jul 2025 Stargate site expansion"},{"label":"Named tenants","value":"OpenAI"}],"reviewStatus":"reviewed","sources":[{"url":"https://openai.com/index/five-new-stargate-sites/","title":"OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites","sourceName":"OpenAI"},{"url":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand","title":"OpenAI Stargate: where the US sites stand","sourceName":"Epoch AI"},{"url":"https://www.reuters.com/business/oracle-cites-force-majeure-shield-itself-controversial-data-center-bloomberg-2026-09-24/","title":"Oracle cites 'force majeure' to shield itself on data center, Bloomberg News reports","sourceName":"Reuters","publishedAt":"2026-09-24"},{"url":"https://www.cnbc.com/2026/09/24/oracle-data-center-force-majeure.html","title":"Oracle shares drop on report it sent 'force majeure' notice about data center project","sourceName":"CNBC","publishedAt":"2026-09-24"},{"url":"https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/","title":"Oracle sends force majeure notice on its New Mexico Stargate data center","sourceName":"TechCrunch","publishedAt":"2026-09-24"},{"url":"https://www.reuters.com/business/energy/oracle-blue-owl-project-delay-sends-ripples-through-ai-financing-sources-say-2026-09-24/","title":"Oracle, Blue Owl project delay sends ripples through AI financing, sources say","sourceName":"Reuters","publishedAt":"2026-09-24"},{"url":"https://www.abqjournal.com/business/oracle-invokes-force-majeure-on-project-jupiter-but-says-data-center-still-on-track/3127907","title":"Oracle invokes force majeure on Project Jupiter, but says data center still on track","sourceName":"Albuquerque Journal","publishedAt":"2026-09-24"},{"url":"https://qz.com/oracle-force-majeure-new-mexico-ai-data-center-092426","title":"Oracle invokes force majeure on New Mexico AI data center","sourceName":"Quartz","publishedAt":"2026-10-03"},{"url":"https://www.theregister.com/on-prem/2026/10/02/power-approval-set-to-delay-oracles-wisconsin-ai-datacenter/5300832","title":"Power approval set to delay Oracle's Wisconsin AI datacenter","sourceName":"The Register","publishedAt":"2026-10-02"},{"url":"https://www.enr.com/articles/63720-oracle-invokes-force-majeure-as-new-mexico-project-jupiter-power-work-faces-hurdles","title":"Oracle Invokes Force Majeure as New Mexico Project Jupiter Power Work Faces Hurdles","sourceName":"Engineering News-Record","publishedAt":"2026-09-25"},{"url":"https://stocktwits.com/news-articles/markets/equity/ai-data-center-delays-new-questions-orcl-be-apld/cZDFMNFRB1s","title":"AI Data Center Delays Raise New Questions For ORCL, BE And APLD, Says IO Fund","sourceName":"Stocktwits","publishedAt":"2026-10-04"},{"url":"https://x.com/venaodiver/status/2107219174644957418","title":"X post on Project Jupiter delays","sourceName":"X/@venaodiver","publishedAt":"2026-10-05"},{"url":"https://www.oracle.com/news/announcement/oracle-issues-rfp-for-2gw-of-renewable-energy-2026-09-08/","title":"Oracle Issues RFP for 2 GW of Renewable Energy in New Mexico","sourceName":"Oracle","publishedAt":"2026-09-08"},{"url":"https://www.abqjournal.com/business/doa-na-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","title":"Doña Ana County's Project Jupiter joins $500 billion Stargate initiative led by OpenAI, Oracle","sourceName":"Albuquerque Journal","publishedAt":"2025-09-23"}],"reviewNote":null,"createdAt":"2026-08-17T18:13:26.103Z","updatedAt":"2026-11-18T03:26:51.533Z","location":{"id":"426e17fd-34c9-4de4-a2c4-c6a9d933fc9b","name":"Santa Teresa","slug":"santa-teresa-new-mexico","kind":"city","parentLocationId":"aa527052-456e-47ba-a76f-5349601e14d5","region":"New Mexico","lat":31.9,"lng":-106.65,"reviewStatus":"reviewed","aliases":[],"collisionRisk":"high","reviewNote":null,"createdAt":"2026-08-17T18:13:25.719Z","updatedAt":"2026-08-21T03:20:12.226Z"},"parties":[{"id":"f55ac6e4-b09a-4c92-bc11-b6f798fe33b3","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":null,"externalName":"STACK Infrastructure","role":"developer","structureNotes":"Developer/builder of Project Jupiter (four buildings).","createdAt":"2026-08-17T18:13:28.498Z","company":null},{"id":"57edcebb-ad90-4ebc-99aa-43c5f171a765","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":"bd3c5b86-a4cf-4655-842d-e32895c87e6b","externalName":"OpenAI","role":"tenant","structureNotes":"Anchor tenant / Stargate program lead.","createdAt":"2026-08-17T18:13:27.729Z","company":{"id":"bd3c5b86-a4cf-4655-842d-e32895c87e6b","name":"OpenAI","slug":"openai"}},{"id":"ec858b3d-226a-4d97-bddb-044beb072c1d","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":"a18eca31-e45d-4693-9cd1-7d306be303fb","externalName":"Oracle","role":"developer","structureNotes":"Oracle-led site under the Stargate expansion; contracts compute to OpenAI.","createdAt":"2026-08-17T18:13:29.258Z","company":{"id":"a18eca31-e45d-4693-9cd1-7d306be303fb","name":"Oracle","slug":"oracle"}},{"id":"fb6fe8d2-de15-4bb8-9455-ab03ce415a79","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":"a9609061-00fd-4d9b-9b2d-ce2d772ab825","externalName":"Nvidia","role":"chip_supplier","structureNotes":"GPU supplier across the Stargate program.","createdAt":"2026-08-17T18:13:30.008Z","company":{"id":"a9609061-00fd-4d9b-9b2d-ce2d772ab825","name":"NVIDIA","slug":"nvidia"}},{"id":"d11d1989-2508-4136-94ff-6d67c2a7d0f3","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":null,"externalName":"BorderPlex Digital Assets","role":"developer","structureNotes":"Austin-based co-developer of Project Jupiter alongside STACK Infrastructure.","createdAt":"2026-08-19T00:28:26.174Z","company":null},{"id":"f936e89e-4d07-41e6-8acf-036c68bc724d","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":null,"externalName":"El Paso Electric","role":"utility","structureNotes":"Regional utility serving the Santa Teresa / Doña Ana County area (WECC).","createdAt":"2026-08-19T00:28:27.302Z","company":null},{"id":"ef118d4d-4757-4880-b707-9bb3205f44da","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","companyId":"d6ac4d62-36f9-4800-8d56-5e82c51594d5","externalName":null,"role":"developer","structureNotes":null,"createdAt":"2026-08-27T22:22:46.378Z","company":{"id":"d6ac4d62-36f9-4800-8d56-5e82c51594d5","name":"Stargate Infrastructure","slug":"stargate-infrastructure"}}],"capacityClaims":[{"id":"afe50ea4-5ba6-4aaa-b4f6-e35ef8648845","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","series":"announced","valueGw":2.2,"asOf":"2026-04-17T00:00:00.000Z","sourceUrl":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand","sourceType":"journalist_report","evidenceTier":"claimed","supersedesId":null,"note":"Epoch AI planned-capacity estimate for Project Jupiter; part of the ~5.5 GW OpenAI attributed to the three Oracle-led sites.","createdAt":"2026-08-17T18:13:26.792Z"},{"id":"31529050-fa17-4d1b-a0ef-7220958a80b7","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","series":"energized","valueGw":0,"asOf":"2026-07-01T00:00:00.000Z","sourceUrl":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":"Epoch AI site tracker shows Project Jupiter (Santa Teresa) at 0 GW as of mid-2026 with foundation work underway. First GW targeted H2 2026, initial operations Q4 2026; nothing energized yet.","createdAt":"2026-08-17T18:33:40.755Z"}],"financialClaims":[{"id":"55ab2e00-5e4d-460c-bdb8-bc5901556490","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","kind":"incentive","label":"Industrial revenue bond approved","valueUsd":null,"capUsd":"165000000000","conditions":"Up to $165 billion industrial revenue bond approved by Doña Ana County commissioners to finance the campus.","asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","sourceType":"journalist_report","evidenceTier":"reported","createdAt":"2026-08-19T00:28:23.011Z"}],"metricClaims":[{"id":"d5c2b714-ea48-41a0-96e7-cd781a10e2ea","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","metricType":"cooling_type","valueNumeric":null,"valueText":"Closed-loop cooling system","unit":null,"grantingJurisdiction":null,"asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:28:25.328Z"},{"id":"9b396c59-bf16-4a81-9a59-1c19eeba7a9a","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","metricType":"jobs_construction","valueNumeric":2500,"valueText":"~2,500 construction jobs over a decade","unit":null,"grantingJurisdiction":null,"asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:28:24.150Z"},{"id":"0fb63f27-fb6f-484b-8cd5-425a995ebe78","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","metricType":"jobs_permanent","valueNumeric":750,"valueText":"~750 permanent positions (salaries ~$75k-$100k)","unit":null,"grantingJurisdiction":null,"asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:28:24.573Z"},{"id":"29757313-e719-4a43-89d0-08608d32432d","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","metricType":"water_gpd","valueNumeric":20000,"valueText":"~20,000 gallons/day proposed domestic water use","unit":null,"grantingJurisdiction":null,"asOf":"2025-06-01T00:00:00.000Z","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:28:24.950Z"}],"powerProjects":[{"id":"2aa1843d-7c65-401d-931c-1a3a73b8eadd","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","name":"Project Jupiter on-site natural gas microgrids","type":"gas","capacityGw":null,"lifecycleState":"under_construction","sourceUrl":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand","evidenceTier":"reported","note":"Two natural gas microgrids to power the campus behind the meter; individual capacity not disclosed (0.0 = unknown, not zero).","createdAt":"2026-08-17T18:13:27.346Z"},{"id":"31e916a7-5db5-436e-848f-361fff595f38","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","name":"On-site natural gas turbine microgrid","type":"gas","capacityGw":null,"lifecycleState":"announced","sourceUrl":"https://www.abqjournal.com/business/doa-ana-countys-project-jupiter-joins-500-billion-stargate-initiative-led-by-openai-oracle/493927","evidenceTier":"reported","note":"Natural gas turbine system with microgrid designed to meet net-zero emission targets by 2045.","createdAt":"2026-08-19T00:28:23.773Z"}],"permits":[{"id":"3f34f73c-d63b-43fe-a3b2-1082639bcf97","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","agency":"NMED AQB","jurisdiction":"New Mexico","kind":"air","permitType":"Air permit (construction, East Microgrid gas turbines)","number":"10732","applicant":"Acoma, LLC","status":"withdrawn","filedDate":"2025-11-17T00:00:00.000Z","decidedDate":null,"docket":null,"regulatedEntityId":null,"sourceUrl":"https://cloud.env.nm.gov/resources/_translator.php/ZDM3ZmUwMjJlYTFhMTQwYTkwZjljMWY0N18yMTYwMTM~.pdf","reviewStatus":"reviewed","reviewNote":"Campus link confirmed 2026-11-18: The state air permit application for the East Microgrid near Santa Teresa was filed by Acoma, LLC, the entity building on-site gas power for Project Jupiter. The agency record shows it under review; the reported April 2026 withdrawal comes from news coverage only. https://cloud.env.nm.gov/resources/_translator.php/ZDM3ZmUwMjJlYTFhMTQwYTkwZjljMWY0N18yMTYwMTM~.pdf \"NMED legal notice: \"Acoma LLC ... has submitted an air quality permit application ... to construct/modify East Microgrid. The application file has been assigned Permit No. 10732 ... approximate location is 3.6 miles S of Santa Teresa in Dona Ana County, NM.\" KANW: \"Acoma, LLC's plans, if approved, would allow Project Jupiter to emit\"; \"Developers sought an individual permit for the microgrids, even though they will support the same development.\"\"","lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:44.347Z","updatedAt":"2026-11-18T18:53:18.910Z"},{"id":"8b4ce8f4-595d-4271-a320-2927ebd69eb1","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","agency":"NMED AQB","jurisdiction":"New Mexico","kind":"air","permitType":"Air permit (construction, West Microgrid gas turbines)","number":"10734","applicant":"Acoma, LLC","status":"withdrawn","filedDate":null,"decidedDate":null,"docket":null,"regulatedEntityId":null,"sourceUrl":"https://cloud.env.nm.gov/resources/_translator.php/NjIyNjQ3YjM3Nzk3YjYwYmRiNDg1YmJhYV8yMTY5OTM~.pdf","reviewStatus":"reviewed","reviewNote":"Campus link confirmed 2026-11-18: The state air permit application for the West Microgrid near Santa Teresa was filed by Acoma, LLC as one of the two gas microgrids supporting Project Jupiter. The agency record shows it under review; the reported withdrawal comes from news coverage only. https://cloud.env.nm.gov/resources/_translator.php/NjIyNjQ3YjM3Nzk3YjYwYmRiNDg1YmJhYV8yMTY5OTM~.pdf \"NMED notice (Spanish): \"Acoma LLC, en 600 Congress Ave Ste 15041, Austin, TX, ha presentado una solicitud de permiso ... No. 10734 ... 4.1 millas al Suroeste de Santa Teresa en el Condado de Dona Ana\". NMED hearing memo, March 23, 2026: \"No. NSR 10734 (IDEA ID No. 41311 - PRN20250001), Acoma, LLC - West Microgrid\". KANW: \"Acoma, LLC's plans, if approved, would allow Project Jupiter to emit\".\"","lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:44.674Z","updatedAt":"2026-11-18T18:53:19.263Z"},{"id":"60a57363-5a6e-45d9-b346-0a7f51b56223","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","agency":"NMED AQB","jurisdiction":"New Mexico","kind":"air","permitType":"Air permit (new source review, Title V major; Bloom solid oxide fuel cell microgrid, 2,462 MW)","number":"NSR 10883","applicant":"Yucca Growth Infrastructure, LLC","status":"pending","filedDate":null,"decidedDate":null,"docket":"AQB 26-57(P)","regulatedEntityId":null,"sourceUrl":"https://www.env.nm.gov/opf/wp-content/uploads/sites/13/2026/07/2026-08-12-AQB-26-57-Amended-Notice-of-Hearing-English-filed.pdf","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:45.051Z","updatedAt":"2026-11-18T02:56:45.051Z"}],"facilities":[{"slug":"oracle-dona-ana-county-new-mexico","name":"Oracle Dona Ana County AI Data Center","status":"under_construction","criticalItMw":null,"facilityType":"hyperscale"}],"incidents":[],"events":[{"id":"2c18d9ff-45cf-42f2-9dc8-508db8b8ff93","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"energization_date_changed","series":null,"oldValue":null,"newValue":"2026-07-01|half","claimId":null,"detail":"intake proposal 37ece247-cf97-443e-b10d-bee04e36eb94","occurredAt":"2026-11-18T03:26:52.121Z","createdAt":"2026-11-18T03:26:52.121Z"},{"id":"bd8f998a-6821-419d-a7f7-8803670d1357","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"NMED AQB NSR 10883: pending","claimId":null,"detail":"Air permit (new source review, Title V major; Bloom solid oxide fuel cell microgrid, 2,462 MW) NSR 10883 recorded from https://www.env.nm.gov/opf/wp-content/uploads/sites/13/2026/07/2026-08-12-AQB-26-57-Amended-Notice-of-Hearing-English-filed.pdf","occurredAt":"2026-11-18T02:56:45.200Z","createdAt":"2026-11-18T02:56:45.200Z"},{"id":"1d979315-afcb-4611-9d97-b96f246d39ee","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"NMED AQB 10734: withdrawn","claimId":null,"detail":"Air permit (construction, West Microgrid gas turbines) 10734 recorded from https://cloud.env.nm.gov/resources/_translator.php/NjIyNjQ3YjM3Nzk3YjYwYmRiNDg1YmJhYV8yMTY5OTM~.pdf","occurredAt":"2026-11-18T02:56:44.855Z","createdAt":"2026-11-18T02:56:44.855Z"},{"id":"8fd9fb84-8494-496f-a0c0-377ab86c16b6","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"NMED AQB 10732: withdrawn","claimId":null,"detail":"Air permit (construction, East Microgrid gas turbines) 10732 recorded from https://cloud.env.nm.gov/resources/_translator.php/ZDM3ZmUwMjJlYTFhMTQwYTkwZjljMWY0N18yMTYwMTM~.pdf","occurredAt":"2026-11-18T02:56:44.525Z","createdAt":"2026-11-18T02:56:44.525Z"},{"id":"d99b0792-efca-4285-ab98-48e27bcd442f","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"merged_duplicate","series":null,"oldValue":"stargate-infrastructure-stargate-dona-ana","newValue":"stargate-dona-ana-county-new-mexico","claimId":null,"detail":"Duplicate campus record stargate-infrastructure-stargate-dona-ana merged into this one (dc-merge-2026-11-17)","occurredAt":"2026-11-18T02:52:11.069Z","createdAt":"2026-11-18T02:52:11.069Z"},{"id":"038c07b3-0292-4d90-a6d9-6d66e22a30ba","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"utility: El Paso Electric","occurredAt":"2026-08-19T00:28:27.743Z","createdAt":"2026-08-19T00:28:27.743Z"},{"id":"e807dfbe-48d6-4954-95be-fb4f9f50202f","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: BorderPlex Digital Assets","occurredAt":"2026-08-19T00:28:26.551Z","createdAt":"2026-08-19T00:28:26.551Z"},{"id":"990ba384-cdf2-4d93-9a73-ed86eba5cb4e","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"incentive: Industrial revenue bond approved","occurredAt":"2026-08-19T00:28:23.386Z","createdAt":"2026-08-19T00:28:23.386Z"},{"id":"267633f0-4272-4458-92cd-bfb54d8a3a93","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"capacity_changed","series":"energized","oldValue":null,"newValue":"0","claimId":"31529050-fa17-4d1b-a0ef-7220958a80b7","detail":null,"occurredAt":"2026-08-17T18:33:41.060Z","createdAt":"2026-08-17T18:33:41.060Z"},{"id":"09b43fea-1fa5-4a6d-94ec-4577d78c388e","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"claim_recorded","series":"energized","oldValue":null,"newValue":"0","claimId":"31529050-fa17-4d1b-a0ef-7220958a80b7","detail":"reported · journalist_report","occurredAt":"2026-08-17T18:33:40.905Z","createdAt":"2026-08-17T18:33:40.905Z"},{"id":"306d1b8a-95d1-4f97-9120-c79074eb1be3","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"chip_supplier: Nvidia","occurredAt":"2026-08-17T18:13:30.391Z","createdAt":"2026-08-17T18:13:30.391Z"},{"id":"5068b9b6-fbc8-4072-aa84-367a47bce8b8","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: Oracle","occurredAt":"2026-08-17T18:13:29.635Z","createdAt":"2026-08-17T18:13:29.635Z"},{"id":"f21653f2-9fd7-4246-a878-49195069876e","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: STACK Infrastructure","occurredAt":"2026-08-17T18:13:28.884Z","createdAt":"2026-08-17T18:13:28.884Z"},{"id":"3ba05252-79e1-46a7-89c0-2e3ad9e93fff","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"tenant: OpenAI","occurredAt":"2026-08-17T18:13:28.116Z","createdAt":"2026-08-17T18:13:28.116Z"},{"id":"37454f11-7ec2-405f-a635-5448a2d8610c","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"capacity_changed","series":"announced","oldValue":null,"newValue":"2.2","claimId":"afe50ea4-5ba6-4aaa-b4f6-e35ef8648845","detail":null,"occurredAt":"2026-08-17T18:13:27.116Z","createdAt":"2026-08-17T18:13:27.116Z"},{"id":"78b067ca-d496-4ebb-8718-984e74e186df","dataCenterId":"4c5d91e2-9598-4b3c-9128-702828bf4251","eventType":"claim_recorded","series":"announced","oldValue":null,"newValue":"2.2","claimId":"afe50ea4-5ba6-4aaa-b4f6-e35ef8648845","detail":"claimed · journalist_report","occurredAt":"2026-08-17T18:13:26.963Z","createdAt":"2026-08-17T18:13:26.963Z"}],"capacity_picture":{"announced_gw":2.2,"contracted_gw":null,"under_construction_gw":null,"energized_gw":0,"announced_minus_energized_gw":2.2,"by_series":{"announced":{"valueGw":2.2,"asOf":"2026-04-17T00:00:00.000Z","evidenceTier":"claimed","sourceUrl":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand"},"contracted":null,"under_construction":null,"energized":{"valueGw":0,"asOf":"2026-07-01T00:00:00.000Z","evidenceTier":"reported","sourceUrl":"https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand"}}},"jsonLd":{"@context":"https://schema.org","@type":"Place","name":"Stargate Doña Ana County / Project Jupiter (New Mexico)","url":"https://registry.deploy.report/datacenters/stargate-dona-ana-county-new-mexico","geo":{"@type":"GeoCoordinates","latitude":31.9,"longitude":-106.65},"address":{"@type":"PostalAddress","addressLocality":"Santa Teresa"}}}