{"id":"1135eddf-79b2-4cde-aa07-753c2624341f","slug":"xai-colossus-2-southaven-mississippi","name":"xAI Colossus 2 Data Center","aliases":[],"locationId":"f4cdf31d-c4d5-44eb-8a8e-f49031f29564","lat":null,"lng":null,"locationPrecision":null,"landStatus":null,"lifecycleState":"partially_energized","powerSourceMix":"behind_the_meter_gas","interconnectionQueueStatus":null,"interconnectionQueueId":null,"expectedEnergizationDate":null,"expectedEnergizationPrecision":null,"expectedEnergizationMilestone":null,"dedicatedSubstation":null,"gridOperator":null,"waterSourceNotes":"Sits too far from the wastewater plant and draws millions of gallons/day of drinking water (about 1.3M gal/day as of early 2026); xAI has announced an ~$80M treatment plant to reuse ~13M gal/day of wastewater. Powered by on-site natural gas turbines.","servingUtility":null,"acreage":null,"totalBuildingSqft":null,"streetAddress":null,"notes":"xAI's second Colossus supercomputer campus in Southaven, Mississippi, part of an expansion of the Memphis-area Colossus complex toward roughly 2 GW. As of 2026 it was powered largely by on-site natural gas turbines, with 46 turbines (about 495 MW) reported operating without air permits and 41 additional turbines permitted in March 2026.","keyFacts":[{"label":"Operator","value":"xAI"},{"label":"Primary workload","value":"Grok training; expansion of the Memphis-area Colossus complex"},{"label":"Announced capacity","value":"About 1.2 GW; about 2 GW with Colossus 1"},{"label":"Lifecycle","value":"Partially energized (2026)"},{"label":"On-site gas turbines (reported)","value":"46 turbines (about 495 MW) ran without air permits; 41 more permitted Mar 2026"},{"label":"Cooling water (reported, early 2026)","value":"Drinking water, about 1.3M gallons a day"},{"label":"Water recycling plant (sources differ)","value":"Earlier reports: about $80M, 13M gal/day; company (Sep 2026): $360M, 10M gal/day."},{"label":"State investment (reported)","value":"Largest private investment in Mississippi history"},{"label":"Regulatory scrutiny","value":"SELC and state regulators flagged unpermitted gas turbines"},{"label":"GPU mix (company-claimed, Sep 2026)","value":"Musk: 110k GB200 and 440k GB300, with more GB300 batches planned through Dec 2026."},{"label":"Battery storage (company-claimed, Sep 2026)","value":"3.3 GWh grid-connected battery"},{"label":"Regional impact (company-claimed, Sep 2026)","value":"$90B+ regional investment; $60M+ 2026 tax revenue; 7,500 jobs supported"},{"label":"Memphis substations (company-claimed, Sep 2026)","value":"$35M for a 150 MW substation and $20M for a second, at no cost to MLGW"},{"label":"Turbine removal (company-claimed, Sep 2026)","value":"State agreed order requires temporary turbines removed by Jul 2027"},{"label":"Campus scale (company-claimed, Sep 2026)","value":"Over 2 GW of compute; 1M+ GPUs planned"},{"label":"Gun Range cluster (company-claimed, Oct 2026)","value":"Musk said Oct 31 that Gun Range will hold about 220k GB300s configured for training, like Macroharder and Minihard, and is tracking to be operational by end of November 2026."},{"label":"Spam cluster (company-claimed, Oct 2026)","value":"Musk said Spam, a building that once housed Hormel products, will hold about 200k GB300s set up for inference with simpler networking and under half the fiber, due in December 2026."},{"label":"Year-end Blackwell total (company-claimed, Oct 2026)","value":"Musk said Colossus 2 will have around 1.2M Blackwell GPUs in total by the end of 2026."}],"reviewStatus":"reviewed","sources":[{"url":"https://www.datacenterdynamics.com/en/news/xai-deploys-19-natural-gas-turbines-at-colossus-2-data-center-in-southaven-mississippi-report/","title":"DCD: xAI deploys gas turbines at Colossus 2, Southaven"},{"url":"https://en.wikipedia.org/wiki/Colossus_(data_center)","title":"Wikipedia: Colossus (data center)"},{"url":"https://www.gem.wiki/Colossus_2_power_station","title":"Global Energy Monitor: Colossus 2 power station"},{"url":"https://www.selc.org/news/xai-built-an-illegal-power-plant-to-power-its-data-center/","title":"SELC: xAI gas turbines and air permits"},{"url":"https://www.governing.com/resilience/wastewater-will-cool-this-memphis-data-center","title":"Wastewater Will Cool This Memphis Data Center","sourceName":"Governing"},{"url":"https://x.com/elonmusk/status/2103329761690865846","title":"Elon Musk: Colossus 1/2 GPU inventory and Q4 GB300 ramp","sourceName":"X (@elonmusk)","publishedAt":"2026-09-24"},{"url":"https://x.com/SawyerMerritt/status/2103332409789776197","title":"Sawyer Merritt: amplifying Musk Colossus inventory post","sourceName":"X (@SawyerMerritt)","publishedAt":"2026-09-24"},{"url":"https://www.spacex.com/Mid-South","title":"SpaceX Mid-South (Colossus community / investment page)","sourceName":"SpaceX (official)","publishedAt":"2026-09-25"},{"url":"https://x.com/SawyerMerritt/status/2103515250737758442","title":"Sawyer Merritt: SpaceX Mid-South site claims (battery pack, water, substations, turbines)","sourceName":"X (@SawyerMerritt)","publishedAt":"2026-09-25"},{"url":"https://www.spacex.com/assets/sites-pages/assets/Memphis-Local-Impact-Report.pdf","title":"Memphis Local Impact Report (SpaceX Mid-South)","sourceName":"SpaceX (official PDF)","publishedAt":"2026-09-25"},{"url":"https://www.spacex.com/assets/sites-pages/assets/Southaven-Local-Impact-Report-web.pdf","title":"Southaven Local Impact Report (SpaceX Mid-South)","sourceName":"SpaceX (official PDF)","publishedAt":"2026-09-25"},{"url":"https://x.com/elonmusk/status/2116587474021691629","title":"Musk: Gun Range training and Spam inference clusters at Colossus 2","sourceName":"Elon Musk on X","publishedAt":"2026-10-31"},{"url":"https://x.com/elonmusk/status/2116596535433871630","title":"Musk: around 1.2M Blackwells at Colossus 2 by end of year","sourceName":"Elon Musk on X","publishedAt":"2026-10-31"},{"url":"https://x.com/elonmusk/status/2116595217138639087","title":"Musk: Gun Range was the local police department gun range","sourceName":"Elon Musk on X","publishedAt":"2026-10-31"},{"url":"https://teslanorth.com/2026/10/31/spacex-spam-gun-range-clusters/","title":"SpaceX's Next AI Supercomputers Are Called Gun Range and Spam","sourceName":"TeslaNorth","publishedAt":"2026-10-31"}],"reviewNote":null,"createdAt":"2026-08-19T00:47:40.420Z","updatedAt":"2026-10-31T20:56:55.434Z","location":{"id":"f4cdf31d-c4d5-44eb-8a8e-f49031f29564","name":"Southaven","slug":"southaven-mississippi","kind":"city","parentLocationId":"9a077787-7f1b-40d2-a9cc-7d45fd07c68f","region":"Mississippi","lat":34.9873822,"lng":-90.0034862,"reviewStatus":"reviewed","aliases":[],"collisionRisk":"high","reviewNote":null,"createdAt":"2026-08-19T00:47:39.977Z","updatedAt":"2026-08-21T03:20:12.226Z"},"parties":[{"id":"fa3e9274-696b-449c-bcd9-ee1337eb451c","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","companyId":"d7bc30aa-e892-42f7-a58a-e172534fec48","externalName":null,"role":"developer","structureNotes":"Owner and operator of Colossus supercomputer campuses","createdAt":"2026-08-19T00:47:44.063Z","company":{"id":"d7bc30aa-e892-42f7-a58a-e172534fec48","name":"xAI","slug":"xai"}},{"id":"ff9f7099-7a22-4035-9695-0bfca1132f3d","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","companyId":"d7bc30aa-e892-42f7-a58a-e172534fec48","externalName":null,"role":"operator","structureNotes":null,"createdAt":"2026-08-19T00:47:45.287Z","company":{"id":"d7bc30aa-e892-42f7-a58a-e172534fec48","name":"xAI","slug":"xai"}}],"capacityClaims":[{"id":"eaa01ac6-1ce8-41dd-854e-cde01ec120c3","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","series":"announced","valueGw":1.2,"asOf":"2026-06-01T00:00:00.000Z","sourceUrl":"https://en.wikipedia.org/wiki/Colossus_(data_center)","sourceType":"journalist_report","evidenceTier":"reported","supersedesId":null,"note":"Colossus 2 targeted at roughly 1.2 GW; combined Memphis-area complex targeted near 2 GW","createdAt":"2026-08-19T00:47:41.557Z"}],"financialClaims":[{"id":"b319aef3-6f1b-4103-ad00-24953c599f13","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","kind":"capex","label":"Reported multi-billion investment (largest private-sector in state history)","valueUsd":null,"capUsd":null,"conditions":"Aggregate figures vary across reports","asOf":"2026-06-01T00:00:00.000Z","sourceUrl":"https://en.wikipedia.org/wiki/Colossus_(data_center)","sourceType":"journalist_report","evidenceTier":"reported","createdAt":"2026-08-19T00:47:42.118Z"},{"id":"5c87689d-d2ee-4ae4-b9d7-f3ea9535736b","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","kind":"capex","label":"Planned wastewater treatment plant (Colossus 2)","valueUsd":"80000000","capUsd":null,"conditions":null,"asOf":"2026-06-01T00:00:00.000Z","sourceUrl":"https://www.governing.com/resilience/wastewater-will-cool-this-memphis-data-center","sourceType":"press","evidenceTier":"reported","createdAt":"2026-08-24T18:42:48.958Z"}],"metricClaims":[{"id":"809a3544-e01a-411a-b9ab-fb1ea053dd95","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","metricType":"gpu_count","valueNumeric":null,"valueText":"Targeting on the order of 1 million Nvidia Blackwell GPUs; several hundred thousand deployed by mid-2026","unit":null,"grantingJurisdiction":null,"asOf":"2026-06-01T00:00:00.000Z","sourceUrl":"https://en.wikipedia.org/wiki/Colossus_(data_center)","sourceType":"journalist_report","evidenceTier":"claimed","supersedesId":null,"note":null,"createdAt":"2026-08-19T00:47:43.288Z"}],"powerProjects":[{"id":"9644e95a-f6cc-4853-b112-81bfb7e36ab5","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","name":"Colossus 2 on-site gas turbine fleet","type":"gas","capacityGw":0.495,"lifecycleState":"partially_energized","sourceUrl":"https://www.gem.wiki/Colossus_2_power_station","evidenceTier":"reported","note":"~46 turbines (~495 MW) reported operating; 41 additional turbines permitted March 2026","createdAt":"2026-08-19T00:47:42.904Z"}],"permits":[{"id":"8699664c-a23e-4326-8f75-59dd303ffef3","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","agency":"MDEQ","jurisdiction":"Mississippi","kind":"air","permitType":"Air construction permit, PSD (41 natural gas turbines)","number":"0680-00119","applicant":"MZX Tech LLC","status":"active","filedDate":null,"decidedDate":"2026-03-11T00:00:00.000Z","docket":"AI 12592","regulatedEntityId":null,"sourceUrl":"https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:48.199Z","updatedAt":"2026-11-18T02:56:48.199Z"},{"id":"16cced13-ddea-4e79-93ab-342b567ed848","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","agency":"MDEQ","jurisdiction":"Mississippi","kind":"air","permitType":"Air general permit coverage (construction modification)","number":"MSR109658","applicant":"MZX Tech LLC","status":"inactive","filedDate":null,"decidedDate":"2025-10-10T00:00:00.000Z","docket":"AI 12592","regulatedEntityId":null,"sourceUrl":"https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","reviewStatus":"reviewed","reviewNote":null,"lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:48.511Z","updatedAt":"2026-11-18T02:56:48.511Z"},{"id":"f079f1cf-8629-45cb-aa56-0be1acb61a23","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","agency":"MDEQ","jurisdiction":"Mississippi","kind":"wastewater","permitType":"Pretreatment permit (industrial discharge to POTW)","number":"MSP092491","applicant":null,"status":"pending","filedDate":null,"decidedDate":null,"docket":"AI 12592","regulatedEntityId":null,"sourceUrl":"https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","reviewStatus":"reviewed","reviewNote":"Campus link confirmed 2026-11-18: The state record lists this pretreatment permit application under MZX Tech LLC at 2875 Stanton Road, Southaven, the xAI affiliate's site. The application is pending; the state asked the applicant for more information on July 9, 2026. https://opc.deq.state.ms.us/ai_info.aspx?ai=12592 \"MDEQ record: \"MZX Tech LLC ... 2875 Stanton Road, Southaven, MS 38671 ... Water | Pretreatment | MSP092491 | 07/09/2026 | Additional Information Requested from Applicant\". DeSoto County News: \"MZX Tech LLC, which is a Wyoming-based affiliate of Musk's artificial intelligence company xAI\" bought \"114.49 acres of property at 2875 Stanton Road South in Southaven\".\"","lastCheckedAt":"2026-11-17T00:00:00.000Z","createdAt":"2026-11-18T02:56:48.876Z","updatedAt":"2026-11-18T18:53:17.652Z"}],"facilities":[{"slug":"xai-southaven-macrohard-desoto-ms","name":"xAI Southaven Data Center (MACROHARD)","status":"announced","criticalItMw":null,"facilityType":"hyperscale"}],"incidents":[{"id":"a949872d-3ad6-4d55-8d85-93bdd2283a00","slug":"xai-colossus-2-naacp-clean-air-act-motion-to-dismiss-denied","kind":"regulatory_action","headline":"Federal judge denies xAI motion to dismiss NAACP Clean Air Act suit over Colossus 2 gas turbines","summary":"The U.S. District Court for the Northern District of Mississippi denied xAI's motion to dismiss the NAACP's Clean Air Act lawsuit over the gas turbine power plant in Southaven, Mississippi that supports the Colossus 2 data center, which the NAACP says operates without required permits. The court held that the plant is not a mobile source and so is not exempt from Clean Air Act permitting, and it rejected xAI's argument that citizen suits are unconstitutional. The court has yet to rule on the NAACP's motion for a preliminary injunction.","occurredAt":"2026-10-30T00:00:00.000Z","reviewStatus":"reviewed","modelId":null,"deploymentId":null,"companyId":"d7bc30aa-e892-42f7-a58a-e172534fec48","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","aliases":[],"collisionRisk":"none","reviewNote":null,"severity":null,"rootCauseCategory":null,"rootCauseDetail":null,"affectedUnitsCount":null,"affectedUnitsBasis":null,"remediationStatus":null,"regulatoryAction":null,"regulatoryBody":null,"propertyDamageEstimateUsd":null,"damageEstimateBasis":null,"bodilyInjurySeverity":null,"fatalityCount":null,"lossCostClass":null,"sourceQualityTier":null,"oshaRecordable":null,"oshaCaseNumber":null,"rootCauseDisclosed":null,"publicDisclosureDate":null,"insuranceClaimPublic":null,"formFactor":null,"latitude":null,"longitude":null,"autonomyClass":null,"legalOutcomeClass":"unknown","createdAt":"2026-11-01T20:39:01.580Z","updatedAt":"2026-11-01T20:39:04.586Z"}],"events":[{"id":"007f6545-b9ec-4fdb-a102-86945d9f484d","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"MDEQ MSP092491: pending","claimId":null,"detail":"Pretreatment permit (industrial discharge to POTW) MSP092491 recorded from https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","occurredAt":"2026-11-18T02:56:49.030Z","createdAt":"2026-11-18T02:56:49.030Z"},{"id":"ab57c2ad-f6ce-402a-8c45-f9fff6a97e44","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"MDEQ MSR109658: inactive","claimId":null,"detail":"Air general permit coverage (construction modification) MSR109658 recorded from https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","occurredAt":"2026-11-18T02:56:48.721Z","createdAt":"2026-11-18T02:56:48.721Z"},{"id":"257a035d-9247-44c5-9714-0c5a20cd478c","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"permit_recorded","series":null,"oldValue":null,"newValue":"MDEQ 0680-00119: active","claimId":null,"detail":"Air construction permit, PSD (41 natural gas turbines) 0680-00119 recorded from https://opc.deq.state.ms.us/ai_info.aspx?ai=12592","occurredAt":"2026-11-18T02:56:48.351Z","createdAt":"2026-11-18T02:56:48.351Z"},{"id":"38bc3e88-cf83-4c38-80c1-2642da1761c3","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"operator: d7bc30aa-e892-42f7-a58a-e172534fec48","occurredAt":"2026-08-19T00:47:45.743Z","createdAt":"2026-08-19T00:47:45.743Z"},{"id":"ecd068bf-4254-4a8c-bb7e-982f83af97f2","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"party_added","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"developer: d7bc30aa-e892-42f7-a58a-e172534fec48","occurredAt":"2026-08-19T00:47:44.516Z","createdAt":"2026-08-19T00:47:44.516Z"},{"id":"610e71a3-db04-4fa2-a7a1-c67992c4f716","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"financial_recorded","series":null,"oldValue":null,"newValue":null,"claimId":null,"detail":"capex: Reported multi-billion investment (largest private-sector in state history)","occurredAt":"2026-08-19T00:47:42.525Z","createdAt":"2026-08-19T00:47:42.525Z"},{"id":"37d9f87e-0e1b-4b64-8dfd-edb165018433","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"capacity_changed","series":"announced","oldValue":null,"newValue":"1.2","claimId":"eaa01ac6-1ce8-41dd-854e-cde01ec120c3","detail":null,"occurredAt":"2026-08-19T00:47:41.871Z","createdAt":"2026-08-19T00:47:41.871Z"},{"id":"00422548-8fce-4d45-a07f-3abc8e64084e","dataCenterId":"1135eddf-79b2-4cde-aa07-753c2624341f","eventType":"claim_recorded","series":"announced","oldValue":null,"newValue":"1.2","claimId":"eaa01ac6-1ce8-41dd-854e-cde01ec120c3","detail":"reported · journalist_report","occurredAt":"2026-08-19T00:47:41.716Z","createdAt":"2026-08-19T00:47:41.716Z"}],"capacity_picture":{"announced_gw":1.2,"contracted_gw":null,"under_construction_gw":null,"energized_gw":null,"announced_minus_energized_gw":1.2,"by_series":{"announced":{"valueGw":1.2,"asOf":"2026-06-01T00:00:00.000Z","evidenceTier":"reported","sourceUrl":"https://en.wikipedia.org/wiki/Colossus_(data_center)"},"contracted":null,"under_construction":null,"energized":null}},"jsonLd":{"@context":"https://schema.org","@type":"Place","name":"xAI Colossus 2 Data Center","url":"https://registry.deploy.report/datacenters/xai-colossus-2-southaven-mississippi","address":{"@type":"PostalAddress","addressLocality":"Southaven"}}}