{"id":"f32365a1-3851-4fe9-a09b-70e4f97557a5","slug":"dataone-vineland-community-opposition-2026-02","kind":"regulatory_action","headline":"Vineland NJ residents protest DataOne 350MW AI data center over noise, emissions, and water concerns","summary":"Approximately 100 Vineland, NJ residents gathered to protest DataOne's under-construction 350MW AI data center, citing concerns about construction noise, air emissions from 32 natural gas engines, water usage in a Wellhead Protected Area, and potential property value decreases. A citizen petition 'Stop the DataONE Data Center in Vineland' was circulated. The Vineland Planning Commission held hearings on the energy plan, with the second phase approved in August 2026. DataOne acquired nearby homes and committed to 95% emissions reduction via pollution-control technology.","occurredAt":"2026-02-08T00:00:00.000Z","reviewStatus":"reviewed","modelId":"61b8ee5b-2267-4d50-8f34-923ef50d454f","deploymentId":"115093a3-d340-40c4-b90d-86992ab99f02","companyId":null,"dataCenterId":null,"aliases":[],"collisionRisk":"none","reviewNote":null,"severity":"moderate","rootCauseCategory":null,"rootCauseDetail":null,"affectedUnitsCount":null,"affectedUnitsBasis":null,"remediationStatus":"in_progress","regulatoryAction":"inquiry_opened","regulatoryBody":"NJ DEP","propertyDamageEstimateUsd":null,"damageEstimateBasis":null,"bodilyInjurySeverity":null,"fatalityCount":null,"lossCostClass":null,"sourceQualityTier":null,"oshaRecordable":null,"oshaCaseNumber":null,"rootCauseDisclosed":null,"publicDisclosureDate":null,"insuranceClaimPublic":null,"formFactor":null,"latitude":null,"longitude":null,"autonomyClass":null,"legalOutcomeClass":"unknown","createdAt":"2026-08-19T21:04:45.011Z","updatedAt":"2026-08-23T15:14:15.796Z","model":{"id":"61b8ee5b-2267-4d50-8f34-923ef50d454f","companyId":"6dc05227-b83c-45e7-9238-9d2591c00358","modelName":"DataOne AI Factory","slug":"dataone-ai-factory","description":"Hyperscale AI data center infrastructure engineered for high-density GPU workloads, featuring direct liquid cooling, power densities of 60-500kW per rack, and PUE of 1.06-1.15. Deployed at 400MW scale in France and 300MW in Vineland, NJ.","formFactor":"other","industryVertical":null,"environment":null,"maturityStage":"production","lifecycleState":"active","supersededByModelId":null,"specs":{},"manufacturerSerial":null,"reviewStatus":"reviewed","sources":[{"url":"https://www.bso.co/all-insights/bso-unveils-dataone-europes-first-giga-scale-ai-hosting-data-centre","label":"BSO Unveils DataOne: Europe's First Giga-Scale AI Hosting Data Centre","title":"BSO Unveils DataOne: Europe's First Giga-Scale AI Hosting Data Centre","mediaType":"article","sourceName":"BSO"}],"aliases":[],"collisionRisk":"low","reviewNote":null,"manufacturerTermForTeleop":null,"keyFacts":[{"label":"Form Factor","value":"other"},{"label":"Maturity","value":"production"},{"label":"Grenoble and Lyon campus","value":"BSO said on 26 November 2024 that DataOne is an acquired Tier-3 campus in Grenoble (Eybens) and Lyon (Villefontaine), France, with 15 MW of IT load across 50,000 square meters and 14 hectares ([BSO](https://www.bso.co/all-insights/bso-unveils-dataone-europes-first-giga-scale-ai-hosting-data-centre))."},{"label":"AI capacity plan","value":"BSO says DataOne is planned to reach 80 MW in April 2025, 200 MW in the fourth quarter of 2026, and 400 MW in late 2028, with direct liquid cooling at 60 to 250 kW per rack and a PUE of 1.06 to 1.15 ([BSO](https://www.bso.co/all-insights/bso-unveils-dataone-europes-first-giga-scale-ai-hosting-data-centre))."}],"createdAt":"2026-08-19T09:05:37.851Z","updatedAt":"2026-10-03T18:00:04.187Z","unitsInFieldClaimed":null,"unitsInFieldVerified":null,"unitsManufacturedClaimed":null,"unitsManufacturedVerified":null,"unitsAsOf":null,"unitsSource":null,"salesModel":null,"priceUndisclosedSince":null,"autonomyClass":null,"autonomyStatement":null,"autonomyStatementSource":null,"demoForensics":null,"exportControlClass":null,"minCommitment":null,"warrantyTerms":null,"serviceModel":null,"productionRateClaimed":null,"productionRateEvidenced":null,"teleopRatioDisclosed":null,"interventionRateDisclosed":null},"deployment":{"id":"115093a3-d340-40c4-b90d-86992ab99f02","modelId":"61b8ee5b-2267-4d50-8f34-923ef50d454f","versionId":null,"locationId":"9d8dcca9-03b6-40dc-a3bd-858dade863da","operatorId":"6dc05227-b83c-45e7-9238-9d2591c00358","ownerId":null,"slug":"dataone-ai-factory-vineland-new-jersey-usa","status":"operational","firstSeen":"2025-03-06T00:00:00.000Z","statusChangeReason":null,"contractType":null,"pilotOutcome":null,"endedAt":null,"unitsOnSite":null,"tasksPerformed":["autonomous_operation"],"shiftStructure":null,"hoursPerDay":8,"siteType":"construction_site","operatorConfirmed":null,"humanSupervisionOnsite":null,"locationPrecisionTier":"verified_coordinates","deploymentScale":"small_2_10","siteEnvironment":"outdoor","operatorType":null,"sourceQualityTier":2,"manufacturerSerial":null,"reviewStatus":"reviewed","sources":[{"url":"https://datacentremagazine.com/articles/dataone-and-nebius-partner-for-new-300mw-ai-data-centre","label":"DataOne and Nebius Partner for New US 300MW AI Data Centre","title":"DataOne and Nebius Partner for New US 300MW AI Data Centre","mediaType":"article","sourceName":"Data Centre Magazine","publishedAt":"2025-03-06"}],"notes":"300MW AI data center built for Nebius with 10-year tenant commitment. Facility generates 85% of its own power using natural gas, with 32 high-efficiency gas engines and 6 diesel generators. Originally planned as 2.4M sqft, scaled to ~718K sqft. Construction underway as of 2026.","keyFacts":[{"label":"Capacity","value":"300MW"},{"label":"Tenant","value":"Nebius (10-year lease)"},{"label":"Power generation","value":"85% on-site natural gas"}],"reviewNote":"Bulk approved — pre-existing deployment record","exposureHours":null,"deploymentMilesEstimate":null,"exposureBasis":null,"customerSegment":"construction","scaleTier":"pilot_lt10","contractValueUsd":null,"contractValueBasis":null,"customerCompanyId":null,"customerExternalName":null,"createdAt":"2026-08-19T09:06:04.602Z","updatedAt":"2026-08-21T14:21:24.837Z"},"company":null,"derived":{"status":"active"},"sources":[{"id":"4509bdef-2abd-4ff5-a977-b08db20b5abf","incidentId":"f32365a1-3851-4fe9-a09b-70e4f97557a5","url":"https://whyy.org/articles/data-center-artificial-intelligence-vineland-new-jersey/","label":"WHYY","publishedAt":"2026-02-10T00:00:00.000Z","notes":null,"title":null,"sourceName":"WHYY","mediaType":"article","videoId":null,"channel":null,"durationSec":null,"timestampSec":null,"createdAt":"2026-08-19T21:04:45.011Z","updatedAt":"2026-08-19T21:04:45.011Z"}],"responses":[],"statusEvents":[{"id":"4cef4004-3ba9-49e5-a481-590eccd49b51","incidentId":"f32365a1-3851-4fe9-a09b-70e4f97557a5","status":"active","reason":null,"source":"agent:recon","effectiveAt":"2026-08-19T21:04:46.139Z","createdAt":"2026-08-19T21:04:46.139Z"}],"jsonLd":{"@context":"https://schema.org","@type":"NewsArticle","@id":"https://registry.deploy.report/incidents/dataone-vineland-community-opposition-2026-02","url":"https://registry.deploy.report/incidents/dataone-vineland-community-opposition-2026-02","headline":"Vineland NJ residents protest DataOne 350MW AI data center over noise, emissions, and water concerns","description":"Approximately 100 Vineland, NJ residents gathered to protest DataOne's under-construction 350MW AI data center, citing concerns about construction noise, air emissions from 32 natural gas engines, water usage in a Wellhead Protected Area, and potential property value decreases. A citizen petition 'Stop the DataONE Data Center in Vineland' was circulated. The Vineland Planning Commission held hearings on the energy plan, with the second phase approved in August 2026. DataOne acquired nearby homes and committed to 95% emissions reduction via pollution-control technology.","identifier":"f32365a1-3851-4fe9-a09b-70e4f97557a5","datePublished":"2026-02-08T00:00:00.000Z","articleSection":"regulatory action","publisher":{"@id":"https://deploy.report/#organization"},"author":{"@id":"https://deploy.report/#organization"}},"framework_metadata":{"framework_schema_version":"0.1.0","verification_status":"verified","maturity_stage":null,"lifecycle_state":null,"architectural_position":{"cohort":null,"sub_cohorts":[]},"within_cohort_verified_vs_claimed_pair":null,"cap_flags":[],"verification_depth":{"sources_count":1,"primary_source_types":[]}}}