Data center comparison
Black Pearl vs Google Midlothian Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Black Pearl | Google Midlothian Campus | |
|---|---|---|
| Announced capacity | not recorded | not recorded |
| Energized capacity | not recorded | 0.27 GW |
| Announced-to-energized gap | not recorded | not recorded |
| Lifecycle | partially energized | partially energized |
| Developer | Cipher Digital Inc. | |
| Location | Wink, Texas, United States | Midlothian, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | not recorded | 540 acres |
On the map
Common questions
Which is further along, Black Pearl or Google Midlothian Campus?
Black Pearl is partially energized; Google Midlothian Campus is partially energized. Energized capacity: not recorded versus 0.27 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Black Pearl and Google Midlothian Campus?
Black Pearl is in Wink, Texas, United States; Google Midlothian Campus is in Midlothian, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.