What are the largest neoclouds by capacity?

The largest neocloud by live, operational power is YTL AI Cloud (about 600 MW active), while the biggest announced buildout is HUMAIN (about 500 MW). Power is the comparable axis; live and announced are ranked separately so a plan is never mistaken for a running site.


Top of the list (live power)

  1. #1
    YTL AI Cloud
    600 MW live
  2. #2
    Sify Technologies
    129 MW live
  3. #3
    SK Telecom GPUaaS
    80 MW live

Ranked by live (operational) power

Neoclouds ranked by live operational data-center power
YTL AI CloudAsia600 MWNVIDIA GB200 NVL72 (count undisclosed)—
Sify TechnologiesAsia129 MW—NVIDIA (H100 / H200 / GB200; deployed count undisclosed)
SK Telecom GPUaaSAsia80 MW1,000+ B200 (Haein cluster)NVIDIA B200 (Petasus)
Voltage ParkNorth America60 MW~24,000 NVIDIA H100 (~35,000+ combined post-Lightning merger)NVIDIA H100 (B200 / GB300 added)
Core42Middle East60 MWup to 35,000 GB300-equivalent (US export-approved); 10,000 via Northern DataNVIDIA H100 / H200 (+ AMD, Cerebras WSE-3)
ePLDTAsia50 MW—NVIDIA H100 / H200
Freedom HoldingAsia48 MW—NVIDIA exascale (Sovereign AI Hub)
OoredooMiddle East26 MW—NVIDIA Hopper / H200
GreenNodeAsia20 MW1,024 H100NVIDIA H100
duMiddle East13 MW—NVIDIA GPUs

Power that is energized and running today. Figures are drawn from each operator’s sourced record.

Ranked by announced / planned power

Neoclouds ranked by announced or contracted data-center power
HUMAINMiddle East500 MW18,000 NVIDIA GB300 (first phase)NVIDIA GB300 (Grace Blackwell Ultra)
NeysaAsia400 MW20,000-25,000 accelerators (target)NVIDIA H100 / L40S
Northern DataEurope250 MW~22,000 NVIDIA H100 / H200 (>85% allocated)NVIDIA H100 / H200
ViettelAsia140 MW96 H200 + 22 DGX B200NVIDIA H200 + DGX B200 (~1.5 exaflops)
Sharon AIOceania132 MW40,000 GB300 (target)NVIDIA H200 + AMD Instinct MI300X
OoredooMiddle East120 MW—NVIDIA Hopper / H200
duMiddle East120 MW—NVIDIA GPUs
Jio PlatformsAsia120 MW>200,000 H100-equivalent at full build (H100-equivalent, not raw count)NVIDIA GB300 (Blackwell Ultra)
Freedom HoldingAsia100 MW—NVIDIA exascale (Sovereign AI Hub)
Siam AIAsia100 MW1,024 H100NVIDIA H100 (to H200 / GB200)
Sustainable Metal CloudAsia84 MW~54,000 NVIDIA GB300 (Project Southgate)NVIDIA H100 (GB300 planned); immersion-cooled
NeevCloudAsia80 MW60,000 GPUs (target)NVIDIA H100 / H200 / B200 / B300
ResetDataOceania72 MW1,024 H200 (AI-F1)NVIDIA H200
Mistral ComputeEurope44 MW~18,000 GPUsNVIDIA GB300
L&T VyomaAsia30 MW10,000 B300 (Chennai)NVIDIA H100 / H200 / B200 (B300 deploying)
KrutrimAsia20 MW—NVIDIA GB200 NVL72 / H100

Contracted or targeted capacity being built. An announcement is not a running site; see the biggest AI data centers for the same distinction at campus level.

GPU fleet disclosed, power not

Common questions

What is the largest neocloud?

By live, operational data-center power, the largest neocloud DEPLOY tracks is YTL AI Cloud at about 600 MW active. By announced or contracted capacity the leader is HUMAIN at about 500 MW. Live and announced are different facts, and both are shown so a plan is never presented as a running site.

Why rank by power instead of GPU count?

Because power is the axis operators actually disclose and the one that is comparable. Most large neoclouds have stopped publishing a single GPU number and now report megawatts, and the GPU figures that do exist mix verified deployments, announced orders, and H100-equivalent estimates that cannot be ranked against each other. Power in megawatts is the honest common denominator; GPU fleet is shown as a secondary column where a credible figure exists.

Which neocloud has the most GPUs?

It depends on whether you count deployed or announced, and the honest answer is that the very largest operators no longer disclose a hard total. Among verified fleets, Northern Data (~22,000 H100/H200) and Voltage Park (~24,000 H100) publish clear numbers; the biggest announced fleets (Lambda's 1,000,000 by 2030, HUMAIN's up to 600,000, Nscale's ~200,000 GB300) are targets, not running hardware.

Are these figures operational or announced?

Both, shown separately. The live table ranks power that is energized and running today; the announced/planned table ranks contracted or targeted capacity that is being built. Each figure is drawn from the operator's sourced registry record, with its status kept explicit rather than blended into one number.