The vocabulary DEPLOY uses to track AI data centers, defined plainly. The distinctions here (announced versus energized, claimed versus verified) are the whole discipline: the sector has the worst announcement inflation in the economy, and precise words are how a claim stays separate from a fact.


Lifecycle stages

Where a campus sits between rumor and running. DEPLOY advances a record only on dated, sourced evidence, so the stage is a claim about progress you can check, not a vibe.

Rumored
Reported but unconfirmed by the developer. The weakest signal, often a single unsourced mention.
Announced
The developer has publicly stated intent to build, usually with a capacity figure. A claim, not construction.
Permitted
Zoning or construction permits are on record with the local jurisdiction.
Financed
Project financing or a definitive investment has been disclosed.
Under construction
Physical site work is underway, ideally corroborated by dated imagery.
Partially energized
Some capacity is drawing power and operating while the rest is still being built.
Energized
The campus is drawing power at its stated capacity. The stage DEPLOY treats as real.
Stalled
Progress has visibly halted with no cancellation announced.
Cancelled
The developer or owner has abandoned the project.

Capacity series

The same campus carries several capacity numbers at once. Keeping them separate is the whole point: a press release quotes the biggest one, and DEPLOY tracks the smallest true one.

Announced capacity
The largest capacity the developer has publicly claimed. A ceiling, not a measurement.
Contracted capacity
Capacity covered by a signed power or tenancy contract.
Under-construction capacity
Capacity with physical build work underway.
Energized capacity
Capacity actually drawing power. The number DEPLOY treats as real.

Evidence tiers

Every capacity figure carries a tier that says how much to trust it, so a developer's claim never renders with the same weight as a confirmed record.

Verified
Confirmed against a primary, first-party, or official record.
Reported
Sourced to credible secondary reporting, not yet primary-confirmed.
Claimed
Asserted by the developer or an interested party, unconfirmed.

Land status

What kind of ground the campus sits on. It shapes the permitting path, the incentives, and how fast a site can move.

Private land
Privately owned land.
Federal land
Land owned by the federal government.
Federal DOE land
US Department of Energy land, often a national-lab or reservation site.
Brownfield
A previously developed or contaminated site being reused.
Former industrial site
A retired industrial site, such as a shuttered power plant or factory.

Power and grid

A data center is a power project with servers attached. These are the terms that decide whether announced capacity ever becomes energized capacity.

Grid operator (ISO / RTO)
The independent system operator that runs the regional grid (ERCOT, PJM, MISO, and others) and its interconnection queue.
Interconnection queue
The waiting list to connect new load or generation to the grid. Queue position and status gate when a campus can energize.
Behind-the-meter
Power generated on-site, bypassing the public grid's interconnection queue.
Announced-to-energized gap
The difference between claimed capacity and capacity actually drawing power. DEPLOY's core metric for a sector with the worst announcement inflation in the economy.
Homes-equivalent
A derived comparison expressing a campus's power as households, at roughly 810,000 homes per gigawatt.
Compute-class estimate
A derived, order-of-magnitude figure of training compute from a sourced chip count, stated relative to a GPT-4-class run. Derived from claims, not measured.

These definitions drive the campus index and every campus record. For how each figure is verified, read the methodology.