Data center comparison

Core Scientific / CoreWeave Muskogee HPC Campus vs Google Pryor (MidAmerica) Data Center Campus

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Core Scientific / CoreWeave Muskogee HPC CampusGoogle Pryor (MidAmerica) Data Center Campus
Announced capacity1.50 GWnot recorded
Energized capacitynot recorded0.09 GW
Announced-to-energized gap1.50 GWnot recorded
Lifecycleunder constructionpartially energized
DeveloperCore ScientificGoogle
LocationMuskogee, Muskogee County, Oklahoma, United StatesPryor, Oklahoma, United States
GridSPPSPP
Acreagenot recorded800 acres

On the map

Common questions

Which is further along, Core Scientific / CoreWeave Muskogee HPC Campus or Google Pryor (MidAmerica) Data Center Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is under construction; Google Pryor (MidAmerica) Data Center Campus is partially energized. Energized capacity: not recorded versus 0.09 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Core Scientific / CoreWeave Muskogee HPC Campus and Google Pryor (MidAmerica) Data Center Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is in Muskogee, Muskogee County, Oklahoma, United States; Google Pryor (MidAmerica) Data Center Campus is in Pryor, Oklahoma, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.