Data center comparison
Core Scientific / CoreWeave Muskogee HPC Campus vs Google Pryor (MidAmerica) Data Center Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Core Scientific / CoreWeave Muskogee HPC Campus | Google Pryor (MidAmerica) Data Center Campus | |
|---|---|---|
| Announced capacity | 1.50 GW | not recorded |
| Energized capacity | not recorded | 0.09 GW |
| Announced-to-energized gap | 1.50 GW | not recorded |
| Lifecycle | under construction | partially energized |
| Developer | Core Scientific | |
| Location | Muskogee, Muskogee County, Oklahoma, United States | Pryor, Oklahoma, United States |
| Grid | SPP | SPP |
| Acreage | not recorded | 800 acres |
On the map
Common questions
Which is further along, Core Scientific / CoreWeave Muskogee HPC Campus or Google Pryor (MidAmerica) Data Center Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is under construction; Google Pryor (MidAmerica) Data Center Campus is partially energized. Energized capacity: not recorded versus 0.09 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Core Scientific / CoreWeave Muskogee HPC Campus and Google Pryor (MidAmerica) Data Center Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is in Muskogee, Muskogee County, Oklahoma, United States; Google Pryor (MidAmerica) Data Center Campus is in Pryor, Oklahoma, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.