Data center campus
Core Scientific / CoreWeave Muskogee HPC Campus
Core Scientific / CoreWeave Muskogee HPC Campus is an AI data center campus developed by Core Scientific in Oklahoma, Muskogee County. 1.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Core Scientific · Private land · SPP · Muskogee, Muskogee County, Oklahoma, United States
Capacity: announced vs energized
Announced-to-energized gap: 1.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2026. 3 months away. Claimed by Core Scientific / CoreWeave (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.50 GW | 2025-06-01 | claimed | journalist report |
| Under construction | 0.07 GW | 2024-11-18 | verified | company filing |
| Under construction | 0.10 GW | 2024-06-01 | reported | press release |
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q2 2025 · not yet energized
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones synthesized from the campus's own capacity ledger, financial claims, and lifecycle events; each chip links to its source. How we source and verify it: satellite construction evidence.
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Facilities tracked
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Location / partners
- Port Muskogee, Oklahoma HPC campus developed by Core Scientific for CoreWeave GPU hosting; groundbreaking with Port Muskogee on Nov 18 2024 (Core Scientific press release)
- Initial building capacity (announced)
- 100 MW facility with about 70 MW critical IT load for NVIDIA GPUs and about 30 MW for ancillary systems; expected operational in 2026 at groundbreaking (Core Scientific, Nov 18 2024)
- Tenant / contract context
- Hosts CoreWeave NVIDIA GPUs for an undisclosed client. Muskogee is part of CoreWeave contracted HPC hosting from Core Scientific totaling 500 MW critical IT load, with stated potential contract value of $8.7B over 12-year contracts (each with two five-year options) (Core Scientific, Nov 18 2024)
- Campus scale plan (announced)
- May 2026 Core Scientific plan to scale Muskogee to about 1.5 GW gross power / about 1.0 GW leasable, with roughly 250 acres secured (Core Scientific, May 6 2026)
- Polaris DS acquisition (announced)
- Agreement to acquire Polaris DS LLC with 440 MW gross power contracted under an Oklahoma Gas & Electric energy agreement; close targeted Q3 2026 subject to approvals (Core Scientific, May 6 2026)
- Delivery milestones (company)
- Leased 70 MW building (NVIDIA GB300 platform) was on track for Q2 2026 customer delivery as of May 2026; second unleased 82.5 MW building under construction with initial delivery targeted Q4 2027 (Core Scientific, May 6 2026)
- Local economic claim (announced)
- Port Muskogee / company materials cite more than $4B capital investment and about $182M local net benefits over the project life, plus about 150 jobs (Core Scientific, Nov 18 2024)
On the data center map
Every tracked data center is on this map, centered on Core Scientific / CoreWeave Muskogee HPC Campus. Pan or zoom out to see how close rivals are building.
- Announced capex
- $8.7B
- Jobs
- 150 permanent reported
- Grid
- SPP · Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.
- Tenant
- CoreWeave
- Land owner
- Port Muskogee
- Cost per MW
- $6M/MW
- Cost per job
- $58M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterMuskogee County(11)·Oklahoma(46)
The deal
- developer
- Core Scientific · Site developer and operator
- land owner
- Port Muskogee · Industrial park / port authority partner
- chip supplier
- NVIDIA · GPUs hosted for CoreWeave
- tenant
- CoreWeave · HPC hosting lessee for Nvidia GPU compute
Power
- Power source
- grid
- Grid operator
- SPP
- Interconnection
- Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.
- Water
- Not published. Core Scientific's own page for the site talks about power, connectivity and expansion room, and mentions cooling only as one of the things the facility provides. It names no cooling method, water source or volume.
The SPP grid demand right now: 27.1 GW (EIA-930, 2026-10-04 12:00). Core Scientific / CoreWeave Muskogee HPC Campus's announced 1.50 GW would be 5.5% of the grid's current load.
County water status: Extreme drought (D3) in Muskogee County, week of 2026-09-29 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Core Scientific / CoreWeave Muskogee HPC Campus sits on private land in Oklahoma, Muskogee County. It connects to the SPP grid, draws on grid power, interconnection is Served by Oklahoma Gas & Electric. Core Scientific announced on 7 May 2026 that it is buying Polaris Technologies for about $421 million in cash, bringing 440 MW of gross power already contracted with OG&E and an on-site substation with it.. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- CoreWeave HPC hosting contracts with Core Scientific (portfolio, not Muskogee alone)
- $8.7B. ~$8.7B potential value over 12-year contracts across six sites; ~590 MW total contracted journalist report
- Total capital investment
- $4B. Core Scientific IR: 'more than $4 billion in capital investment' company filing
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Facilities at this campus
Timeline
- Aug 2026party linkedtenant: linked externalName "CoreWeave" to company coreweave
- Oct 2026Current: Under construction
Sources
- DCD: CoreWeave and Core Scientific break ground in Muskogee
- Oklahoma Commerce: Muskogee 100 MW HPC groundbreaking
- Blockspace: Core Scientific Oklahoma expansion
- Muskogee Data Center power station · Global Energy Monitor
- Core Scientific acquires cryptomine in Muskogee to expand AI data center campus · Data Center Dynamics
- Core Scientific Acquires Polaris Technologies & 440 MW Grid Connection · Energy.Media
- Oklahoma Data Center | High-Density in Muskogee · Core Scientific
- Core Scientific and Port Muskogee Break Ground on 100 MW HPC Data Center
- Core Scientific Plans Expansion to 1.5 GW Gross Power at Muskogee Campus
6db978fa-8c95-4c64-96a1-0a4271e38943 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Core Scientific / CoreWeave Muskogee HPC Campus?
How much power will Core Scientific / CoreWeave Muskogee HPC Campus use?
Who is building Core Scientific / CoreWeave Muskogee HPC Campus?
Is Core Scientific / CoreWeave Muskogee HPC Campus operating yet?
How verified is the data on Core Scientific / CoreWeave Muskogee HPC Campus?
Deploy Watch
Track Core Scientific / CoreWeave Muskogee HPC Campus on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Core Scientific / CoreWeave Muskogee HPC Campus: AI data center campus record. Retrieved October 4, 2026, from https://registry.deploy.report/datacenters/coreweave-core-scientific-muskogee-oklahoma
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/coreweave-core-scientific-muskogee-oklahoma.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/coreweave-core-scientific-muskogee-oklahoma
- Data documentation: /data
- Query this programmatically: Deploy MCP