Data center comparison
Core Scientific / CoreWeave Muskogee HPC Campus vs Poolside Project Horizon
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Core Scientific / CoreWeave Muskogee HPC Campus | Poolside Project Horizon | |
|---|---|---|
| Announced capacity | 1.50 GW | 2 GW |
| Energized capacity | not recorded | 0 GW |
| Announced-to-energized gap | 1.50 GW | 2 GW |
| Lifecycle | under construction | stalled |
| Developer | Core Scientific | Poolside AI |
| Location | Muskogee, Muskogee County, Oklahoma, United States | Fort Stockton, Texas, United States |
| Grid | SPP | ERCOT |
| Acreage | not recorded | 568 acres |
On the map
Common questions
Which is bigger, Core Scientific / CoreWeave Muskogee HPC Campus or Poolside Project Horizon?
By announced capacity, Poolside Project Horizon is larger: 2 GW versus 1.50 GW. Announced figures are claims, not built capacity.
Which is further along, Core Scientific / CoreWeave Muskogee HPC Campus or Poolside Project Horizon?
Core Scientific / CoreWeave Muskogee HPC Campus is under construction; Poolside Project Horizon is stalled. Energized capacity: not recorded versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Core Scientific / CoreWeave Muskogee HPC Campus and Poolside Project Horizon?
Core Scientific / CoreWeave Muskogee HPC Campus is in Muskogee, Muskogee County, Oklahoma, United States; Poolside Project Horizon is in Fort Stockton, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.