Data center comparison
Core Scientific / CoreWeave Muskogee HPC Campus vs Galaxy Helios Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Core Scientific / CoreWeave Muskogee HPC Campus | Galaxy Helios Campus | |
|---|---|---|
| Announced capacity | 1.50 GW | 1.60 GW |
| Energized capacity | not recorded | 0.13 GW |
| Announced-to-energized gap | 1.50 GW | 1.47 GW |
| Lifecycle | under construction | partially energized |
| Developer | Core Scientific | CoreWeave |
| Location | Muskogee, Muskogee County, Oklahoma, United States | Afton, Texas, United States |
| Grid | SPP | ERCOT |
| Acreage | not recorded | 2,200 acres |
On the map
Common questions
Which is bigger, Core Scientific / CoreWeave Muskogee HPC Campus or Galaxy Helios Campus?
By announced capacity, Galaxy Helios Campus is larger: 1.60 GW versus 1.50 GW. Announced figures are claims, not built capacity.
Which is further along, Core Scientific / CoreWeave Muskogee HPC Campus or Galaxy Helios Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is under construction; Galaxy Helios Campus is partially energized. Energized capacity: not recorded versus 0.13 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Core Scientific / CoreWeave Muskogee HPC Campus and Galaxy Helios Campus?
Core Scientific / CoreWeave Muskogee HPC Campus is in Muskogee, Muskogee County, Oklahoma, United States; Galaxy Helios Campus is in Afton, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.