Data center comparison
Google Midlothian Campus vs GW Ranch
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Google Midlothian Campus | GW Ranch | |
|---|---|---|
| Announced capacity | not recorded | 1 GW |
| Energized capacity | 0.27 GW | not recorded |
| Announced-to-energized gap | not recorded | 1 GW |
| Lifecycle | partially energized | permitted |
| Developer | Pacifico Energy | |
| Location | Midlothian, Texas, United States | Fort Stockton, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 540 acres | 8,000 acres |
On the map
Common questions
Which is further along, Google Midlothian Campus or GW Ranch?
Google Midlothian Campus is partially energized; GW Ranch is permitted. Energized capacity: 0.27 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Google Midlothian Campus and GW Ranch?
Google Midlothian Campus is in Midlothian, Texas, United States; GW Ranch is in Fort Stockton, Texas, United States. Each record on DEPLOY is sourced and dated.