Data center comparison
Google Midlothian Campus vs Poolside Project Horizon
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Google Midlothian Campus | Poolside Project Horizon | |
|---|---|---|
| Announced capacity | not recorded | 2 GW |
| Energized capacity | 0.27 GW | 0 GW |
| Announced-to-energized gap | not recorded | 2 GW |
| Lifecycle | partially energized | stalled |
| Developer | Poolside AI | |
| Location | Midlothian, Texas, United States | Fort Stockton, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | 540 acres | 568 acres |
On the map
Common questions
Which is further along, Google Midlothian Campus or Poolside Project Horizon?
Google Midlothian Campus is partially energized; Poolside Project Horizon is stalled. Energized capacity: 0.27 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Google Midlothian Campus and Poolside Project Horizon?
Google Midlothian Campus is in Midlothian, Texas, United States; Poolside Project Horizon is in Fort Stockton, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.