Data center comparison
Project Cardinal Data Center Campus — Yorkville vs PsiQuantum Chicago Quantum Campus at IQMP
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Project Cardinal Data Center Campus — Yorkville | PsiQuantum Chicago Quantum Campus at IQMP | |
|---|---|---|
| Announced capacity | 1.80 GW | not recorded |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 1.80 GW | not recorded |
| Lifecycle | permitted | under construction |
| Developer | Pioneer Development, LLC | PsiQuantum |
| Location | Yorkville, Illinois, United States | Chicago, Cook County, Illinois, United States |
| Grid | PJM | PJM |
| Acreage | 1,037 acres | not recorded |
On the map
Common questions
Which is further along, Project Cardinal Data Center Campus — Yorkville or PsiQuantum Chicago Quantum Campus at IQMP?
Project Cardinal Data Center Campus — Yorkville is permitted; PsiQuantum Chicago Quantum Campus at IQMP is under construction. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Project Cardinal Data Center Campus — Yorkville and PsiQuantum Chicago Quantum Campus at IQMP?
Project Cardinal Data Center Campus — Yorkville is in Yorkville, Illinois, United States; PsiQuantum Chicago Quantum Campus at IQMP is in Chicago, Cook County, Illinois, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.