Data center comparison
Aligned Conesville Industrial Park Campus vs QTS Data Centers — Van Wert, Ohio Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Aligned Conesville Industrial Park Campus | QTS Data Centers — Van Wert, Ohio Campus | |
|---|---|---|
| Announced capacity | not recorded | 0.50 GW |
| Energized capacity | not recorded | 0 GW |
| Announced-to-energized gap | not recorded | 0.50 GW |
| Lifecycle | under construction | announced |
| Developer | Aligned Data Centers | QTS Data Centers |
| Location | Conesville, Coshocton County, Ohio, United States | Van Wert, Ohio, United States |
| Grid | PJM | PJM |
| Acreage | 197 acres | not recorded |
On the map
Common questions
Which is further along, Aligned Conesville Industrial Park Campus or QTS Data Centers — Van Wert, Ohio Campus?
Aligned Conesville Industrial Park Campus is under construction; QTS Data Centers — Van Wert, Ohio Campus is announced. Energized capacity: not recorded versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Aligned Conesville Industrial Park Campus and QTS Data Centers — Van Wert, Ohio Campus?
Aligned Conesville Industrial Park Campus is in Conesville, Coshocton County, Ohio, United States; QTS Data Centers — Van Wert, Ohio Campus is in Van Wert, Ohio, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.