DEPLOYDatabase

Data center campus

Aligned Conesville Industrial Park Campus

Aligned Conesville Industrial Park Campus is a tracked AI data center campus in Ohio, Coshocton County. Aligned Data Centers mega-scale campus inside the Conesville Industrial Park, Coshocton County, Ohio, on a ~197-acre parcel adjacent to the former AEP Conesville Power Plant (brownfield revitalization). Company press rel

Under construction · Aligned Data Centers · Former industrial site · PJM · Conesville, Coshocton County, Ohio, United States


Capacity: announced vs energized

Announced
not recorded
Contracted
not recorded
Under construction
not recorded
Energized
not recorded

Expected online: July 1, 2026. 5 months past the claimed date, with no energized capacity on record..

Aligned Conesville Industrial Park Campus capacity claims
Source

Key facts

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Operator / developer
Aligned Data Centers
Location
Conesville Industrial Park, Coshocton County, Ohio; next to the former AEP Conesville plant
Timeline
Groundbreaking Sep 30 2025; initial capacity targeted mid-2026
Land status
Brownfield revitalization
Site size
197 acres
Investment (company-claimed)
Multi-billion dollar phased development
Foundational customer (company-claimed)
First building has an unnamed foundational customer
Jobs (company-claimed)
Thousands of construction jobs and hundreds of permanent roles
Ohio portfolio
Aligned's third Ohio campus
Grid
PJM territory

On the data center map

Every tracked data center is on this map, centered on Aligned Conesville Industrial Park Campus. Pan or zoom out to see how close rivals are building.

Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.

Free to use on your site, with a link back to DEPLOY.
The story of Aligned Conesville Industrial Park Campus
Grid
PJM · due 2026
Tenant
Unnamed foundational customer

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterCoshocton County(4)·Ohio(141)

The deal

developer
Aligned Data Centers · Developing the Conesville Industrial Park multi-building campus.
tenant
Unnamed foundational customer · Aligned says the first data center has secured a foundational customer; counterparty not named in the Jul 24, 2025 release.
grid operator
PJM Interconnection · Campus sits in PJM territory (registry gridOperator).

Power

Power source
grid
Grid operator
PJM
Interconnection

The PJM grid demand right now: 94.1 GW (EIA-930, 2026-11-19 16:00).

County water status: Abnormally dry (D0) in Coshocton County, week of 2026-11-17 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

Aligned Conesville Industrial Park Campus sits on former industrial site in Ohio, Coshocton County. It connects to the PJM grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Regulatory paper trail

The permits, filings and rules on record for this site and its jurisdiction. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States

Timeline

  1. Sep 2026
    party added
    grid_operator: PJM Interconnection
  2. Nov 2026
    Current: Under construction

Sources

40512f0c-0bba-4853-8ea5-420accc2e328 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Aligned Conesville Industrial Park Campus?
Aligned Conesville Industrial Park Campus is an AI data center campus tracked on the DEPLOY registry, located in Conesville. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
Who is building Aligned Conesville Industrial Park Campus?
Aligned Data Centers is recorded as a party to Aligned Conesville Industrial Park Campus on the DEPLOY registry. The full party list, with each role, is on the record.
Is Aligned Conesville Industrial Park Campus operating yet?
As of the most recent verification on the DEPLOY registry, Aligned Conesville Industrial Park Campus is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Aligned Conesville Industrial Park Campus?
This record has been checked against its cited sources by automated agents for the indexed registry; it has not been individually reviewed by a person. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Aligned Conesville Industrial Park Campus on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Aligned Conesville Industrial Park Campus: AI data center campus record. Retrieved November 20, 2026, from https://registry.deploy.report/datacenters/aligned-conesville-ohio

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces