Grid operator
AI data centers on the PJM grid
Every tracked AI data center campus interconnecting to the PJM grid, with combined announced-vs-energized capacity and the grid's live demand. Each figure is individually dated and sourced.
On this grid
Campuses
16
Announced (combined)
26.10 GW
Energized (combined)
1.41 GW
Grid demand now
98.4 GW
The PJM grid is pulling 98.4 GW right now (EIA-930, 2026-08-20 06:00). If every announced campus on this grid energized fully, their combined 26.10 GW would be 26.5% of the grid's current load. Announced numbers are claims, not built capacity; see the methodology.
Campuses on this grid
See every campus on the national data center map, browse the full campus index, or read the verified-vs-claimed methodology.