AI data centers on the PJM grid

Every tracked AI data center campus interconnecting to the PJM grid, with combined announced-vs-energized capacity and the grid's live demand. Each figure is individually dated and sourced.


On this grid

Campuses
20
Announced (combined)
27.30 GW
Energized (combined)
1.41 GW
Grid demand now
96.8 GW

The PJM grid is pulling 96.8 GW right now (EIA-930, 2026-11-20 02:00). If every announced campus on this grid energized fully, their combined 27.30 GW would be 28.2% of the grid's current load. Announced numbers are claims, not built capacity; see the methodology.