Data center campus

Amazon Project Rainier Data Center (New Carlisle)

Amazon Project Rainier Data Center is an announced AI data center campus. 2.20 GW of capacity has been announced; 0.91 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · Private land · PJM · New Carlisle, Indiana, United States


Capacity: announced vs energized

Announced
2.20 GW
claimed
Contracted
not recorded
Under construction
1.93 GW
claimed
Energized
0.91 GW
reported

Announced-to-energized gap: 1.29 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Amazon Project Rainier Data Center (New Carlisle) capacity claims
Source
Announced2.20 GW2025-10-29claimedjournalist report
Energized0.91 GW2026-03-23reportedjournalist report
Under construction1.93 GW2028-01-01claimedjournalist report

The deal

developer
Amazon Web Services · Owner-operator of the ~1,200-acre New Carlisle campus.
tenant
Anthropic · Primary tenant; trains and serves Claude models on the cluster.
chip supplier
AWS Annapurna Labs (Trainium2/Trainium3) · Amazon's in-house AI accelerators; ~500k Trainium2 chips deployed.
investor
Amazon · Strategic investor in Anthropic in addition to infrastructure provider.
utility
Indiana Michigan Power (AEP) · Grid supply and high-voltage interconnection.
grid operator
PJM · I&M operates within PJM Interconnection.

Power

Power source
grid
Grid operator
PJM
Interconnection

Indiana Michigan Power (AEP) grid supply, 2.20 GW grid ppa, Under construction. I&M (AEP subsidiary) partnered with AWS to deliver high-voltage infrastructure; grid-supplied within PJM.

Financial structure

Amazon Project Rainier investment (announced)
$11B. Announced at Oct 2025 opening; Epoch estimates ~$34.5B deployed to date, ~$72.9B at full buildout. journalist report
Anthropic 10-year compute commitment
$100B. Anthropic to spend >$100B on compute over 10 years and reserve up to 5 GW of Trainium capacity. journalist report

Sources

49044b3a-b534-4134-b8b4-461e0eb98bf2 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.