Amazon (AWS) Boardman Data Center Campus
Amazon (AWS) Boardman Data Center Campus is an announced AI data center campus. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · greenfield · WECC · Boardman, Oregon, United States
Capacity: announced vs energized
Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 1 GW | 2024-01-01 | reported | journalist report |
The deal
- operator
- Amazon Web Services
- utility
- PacifiCorp (Pacific Power) · Local retail utility
- utility
- Bonneville Power Administration · Regional balancing authority (WECC)
Power
- Power source
- mixed
- Grid operator
- WECC
- Interconnection
Bloom Energy fuel cells (Morrow County AWS site), 0.02 GW gas, Announced. Reported ~24 MW behind-the-meter fuel cells supplementing a site with ~40 MW grid available.
Sources
- Morrow County OKs $1 billion deal in tax breaks with Amazon
- Amazon to receive $1 billion in tax breaks in eastern Oregon for new data centers
11de3cbb-092d-403c-86fb-37f506ab6361 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.