Data center campus

Nebius Vineland AI Data Center

Nebius Vineland AI Data Center is an announced AI data center campus. 0.30 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · Private land · PJM · Vineland, New Jersey, United States


Capacity: announced vs energized

Announced
0.30 GW
claimed
Contracted
not recorded
Under construction
not recorded
Energized
not recorded

Announced-to-energized gap: 0.30 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Nebius Vineland AI Data Center capacity claims
Source
Announced0.30 GW2025-09-01claimedpress release

The deal

operator
Nebius Group N.V. · Ticker NBIS; build-to-suit model
offtaker
Microsoft · Multi-year GPU capacity agreement, up to ~$17.4B total contract value through 2031 per 20-F
chip supplier
NVIDIA · Blackwell GPUs

Power

Power source
behind the meter gas
Grid operator
PJM
Interconnection

Vineland on-site Bloom Energy fuel cells / gas engines, gas, Under construction. Behind-the-meter generation; exact MW not disclosed

Sources

3ba39da0-2226-4e26-b5c6-9299214fd403 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.