Data center campus
Nebius Independence AI Factory Campus
Nebius Independence AI Factory Campus is an announced AI data center campus. 1.20 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · greenfield · SPP · Independence, Missouri, United States
Capacity: announced vs energized
Announced
1.20 GW
reported
Contracted
not recorded
Under construction
not recorded
Energized
not recorded
Announced-to-energized gap: 1.20 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 1.20 GW | 2026-03-04 | reported | journalist report |
The deal
- operator
- Nebius Group N.V. · Ticker NBIS
- utility
- Independence Power & Light · Municipal utility, SPP
Power
- Power source
- grid
- Grid operator
- SPP
- Interconnection
Sources
- Nebius Group N.V. Form 20-F FY2025
- Nebius breaks ground on 400-acre data center campus in Independence, Missouri
- Nebius Data Center FAQs
6e1eef61-b5b6-431c-82d3-ff9a9c9bfa29 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.