Data center campus

Meta Prometheus Data Center (New Albany)

Meta Prometheus Data Center is an announced AI data center campus. 1 GW of capacity has been announced; 0.50 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · Private land · PJM · New Albany, Ohio, United States


Capacity: announced vs energized

Announced
1 GW
claimed
Contracted
not recorded
Under construction
not recorded
Energized
0.50 GW
reported

Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Meta Prometheus Data Center (New Albany) capacity claims
Source
Announced1 GW2026-05-01claimedjournalist report
Energized0.50 GW2026-05-01reportedjournalist report

The deal

developer
Meta Platforms · Owner-operator; New Albany campus.
tenant
Meta Platforms · Self-tenant; AI supercluster compute.
utility
AEP Ohio · Grid interconnection utility.
grid operator
PJM · AEP Ohio operates within PJM Interconnection.
construction
Williams Companies · Building the Socrates South behind-the-meter gas facility.
utility
Vistra / Constellation / Oklo / TerraPower · Nuclear power counterparties (PPAs and future SMR/advanced-reactor deals).

Power

Power source
mixed
Grid operator
PJM
Interconnection

Williams Socrates South (behind-the-meter gas), 0.20 GW gas, Under construction. ~307.5 MW nameplate, ~258 MW at design ambient, 200 MW firm; construction began June 2025, targeted before end of 2026.

Vistra Ohio nuclear PPA, 2.10 GW nuclear, Financed. Meta to buy >2.1 GW from two Vistra nuclear plants in Ohio plus expansions; also TerraPower, Oklo (Aurora Powerhouse, Pike County) and Constellation agreements.

Contracted renewables (Ohio solar / Indiana wind), 0.80 GW solar storage, Financed. Over 800 MW of renewable energy contracted.

Financial structure

Meta New Albany campus investment (to date)
$1.5B. Cumulative since breaking ground in 2017; understates full Prometheus buildout. journalist report

Sources

d7c13110-4def-4903-9828-a30b405f3afb · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.