Meta Hyperion Data Center (Richland Parish)

Meta Hyperion Data Center is an announced AI data center campus. 5 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Private land · MISO · Delhi, Louisiana, United States


Capacity: announced vs energized

Announced
5 GW
claimed
Contracted
not recorded
Under construction
2 GW
claimed
Energized
0 GW
reported

Announced-to-energized gap: 5 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Meta Hyperion Data Center (Richland Parish) capacity claims
Source
Announced5 GW2026-07-13claimedpress release
Energized0 GW2026-08-17reportedjournalist report
Under construction2 GW2026-07-13claimedjournalist report

The deal

developer
Meta Platforms · 20% owner of build JV; owner-operator of the compute.
tenant
Meta Platforms · Self-tenant; AI/superintelligence compute.
financier
Blue Owl Capital · 80% of the $27B JV that finances/builds/operates the physical campus.
utility
Entergy Louisiana · Building the gas generation fleet (10 plants / ~7.5 GW) to serve the load.
grid operator
MISO · Entergy Louisiana operates within MISO.

Power

Power source
mixed
Grid operator
MISO
Interconnection

Entergy Louisiana new gas plants (first three), 2.26 GW gas, Permitted. First three CCGT plants approved by the Louisiana PSC in 2025 to serve Hyperion.

Entergy Louisiana additional gas plants (seven more), 5.30 GW gas, Announced. Seven additional plants (~5.3 GW) sought; brings total to 10 plants / ~7.5 GW. LPSC approval pending.

Meta-funded clean/renewable generation + battery storage, 2.50 GW solar storage, Announced. Meta commits to fund up to 2.5 GW of clean and renewable energy including battery storage; also nuclear uprates.

Financial structure

Total Meta investment in Richland Parish
$50B. Nearly 10 million sq ft campus; up from $10B originally announced Dec 2024. journalist report
Blue Owl Capital JV (Meta 20% / Blue Owl 80%)
up to $27B. Oct 2025 JV to finance, build and operate the campus; up to $27B total development cost. journalist report

Sources

89efdd2f-1ec9-47a1-bb7c-a1ad597bc991 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.