Data center comparison
Aligned Conesville Industrial Park Campus vs Meta Prometheus Data Center
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Aligned Conesville Industrial Park Campus | Meta Prometheus Data Center | |
|---|---|---|
| Announced capacity | not recorded | 1 GW |
| Energized capacity | not recorded | 0.50 GW |
| Announced-to-energized gap | not recorded | 0.50 GW |
| Lifecycle | under construction | partially energized |
| Developer | Aligned Data Centers | Meta |
| Location | Conesville, Coshocton County, Ohio, United States | New Albany, Ohio, United States |
| Grid | PJM | PJM |
| Acreage | 197 acres | not recorded |
On the map
Common questions
Which is further along, Aligned Conesville Industrial Park Campus or Meta Prometheus Data Center?
Aligned Conesville Industrial Park Campus is under construction; Meta Prometheus Data Center is partially energized. Energized capacity: not recorded versus 0.50 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Aligned Conesville Industrial Park Campus and Meta Prometheus Data Center?
Aligned Conesville Industrial Park Campus is in Conesville, Coshocton County, Ohio, United States; Meta Prometheus Data Center is in New Albany, Ohio, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.