CyrusOne DFW10 Whitney / Thad Hill Powered Land vs Google Midlothian Campus
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| CyrusOne DFW10 Whitney / Thad Hill Powered Land | Google Midlothian Campus | |
|---|---|---|
| Announced capacity | 0.40 GW | not recorded |
| Energized capacity | not recorded | 0.27 GW |
| Announced-to-energized gap | 0.40 GW | not recorded |
| Lifecycle | under construction | partially energized |
| Developer | CyrusOne | |
| Location | Whitney, Texas, United States | Midlothian, Texas, United States |
| Grid | ERCOT | ERCOT |
| Acreage | not recorded | 540 acres |
On the map
Common questions
Which is further along, CyrusOne DFW10 Whitney / Thad Hill Powered Land or Google Midlothian Campus?
CyrusOne DFW10 Whitney / Thad Hill Powered Land is under construction; Google Midlothian Campus is partially energized. Energized capacity: not recorded versus 0.27 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are CyrusOne DFW10 Whitney / Thad Hill Powered Land and Google Midlothian Campus?
CyrusOne DFW10 Whitney / Thad Hill Powered Land is in Whitney, Texas, United States; Google Midlothian Campus is in Midlothian, Texas, United States. Each record on DEPLOY is sourced and dated.