Data center campus

CyrusOne DFW10 Whitney / Thad Hill Powered Land

CyrusOne DFW10 Whitney / Thad Hill Powered Land is an AI data center campus developed by CyrusOne in Texas, Whitney. 0.40 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · CyrusOne · greenfield · ERCOT · Whitney, Texas, United States


Capacity: announced vs energized

Announced-to-energized gap: 0.40 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: Q4 2026. 3 months away. Claimed by CyrusOne / Calpine (source).

CyrusOne DFW10 Whitney / Thad Hill Powered Land capacity claims
Source
Announced0.40 GW2025-12-09reportedjournalist report
Announced0.19 GW2025-07-30reportedpress release
Contracted0.40 GW2025-11-03reportedpress release
Contracted0.19 GW2025-07-30reportedutility filing
Under construction0.14 GW2026-06-01reportedjournalist report

Key facts

0.40 GW

Announced

0 GW

Energized

CyrusOne

Developer

ERCOT

Grid

0.40 GW

Announced-to-energized gap

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

190 MW Phase 1 Powered Land / Q4 2026 target (primary)
On Jul 30, 2025, Calpine and CyrusOne announced a 190 MW agreement for a new data center adjacent to Calpine's Thad Hill Energy Center in Bosque County, Texas (campus named DFW10), securing power, grid connection, and land. The release says the facility was under construction and expected operational by Q4 2026, with first-phase footprint more than 190,000 sq ft and the project framed as a $1.2 billion infrastructure investment. CyrusOne is described as backed by GIP (part of BlackRock) and KKR (Calpine, Jul 30 2025)
Calpine PLC / up to 400 MW Bosque capability (primary)
The July 2025 Calpine release states Calpine's ~9,000 MW ERCOT generation and wholesale/retail platform would be capable of delivering up to 400 MW to data centers located in Bosque, Texas, under its Powered Land Capabilities suite, and positions the deal as supporting ERCOT grid-emergency response capability at the CyrusOne campus (Calpine, Jul 30 2025)
Phase 2 adds 210 MW to 400 MW total (primary)
On Nov 3, 2025, CyrusOne and Calpine announced Phase 2 of the powered-land agreement, adding 210 MW to the original 190 MW for a completed 400 MW power, grid-connection, and land package serving the Thad Hill-adjacent CyrusOne facility still targeted for Q4 2026 energization. Quotes emphasize coordinated operations to curtail in scarcity periods for ERCOT reliability (CyrusOne, Nov 3 2025)

On the data center map

Every tracked data center is on this map, centered on CyrusOne DFW10 Whitney / Thad Hill Powered Land. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of CyrusOne DFW10 Whitney / Thad Hill Powered Land
Announced capex
$1.2B
Derived
Cost per MW
$3M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterTexas(606)

The deal

developer
CyrusOne · Backed by GIP/BlackRock and KKR
utility
Calpine · Owns Thad Hill Energy Center; power + land agreement
financier
Global Infrastructure Partners (BlackRock) · CyrusOne owner
financier
KKR · CyrusOne owner
grid operator
ERCOT · Thad Hill Energy Center serves ERCOT; firm grid connection provided

Power

Power source
grid
Grid operator
ERCOT
Interconnection

Thad Hill Energy Center, 0.25 GW gas, Energized. Existing ~250 MW Calpine combined-cycle plant

The Texas (ERCOT) grid demand right now: 59.4 GW (EIA-930, 2026-10-02 04:00). CyrusOne DFW10 Whitney / Thad Hill Powered Land's announced 0.40 GW would be 0.7% of the grid's current load.

County water status: Severe drought (D2) in Hill County, week of 2026-09-22 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

CyrusOne DFW10 Whitney / Thad Hill Powered Land sits on greenfield in Texas, Whitney. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

DFW10 campus investment
$1.2B press release

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

Investment, workforce and specs

Capex
$1.2 billion infrastructure investment source

Timeline

  1. Aug 2026
    party added
    grid_operator: ERCOT
  2. Oct 2026
    Current: Under construction

Sources

0402b2da-aad8-4d33-a8dd-6d531b7a407a · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is CyrusOne DFW10 Whitney / Thad Hill Powered Land?
CyrusOne DFW10 Whitney / Thad Hill Powered Land is an AI data center campus tracked on the DEPLOY registry, located in Whitney. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will CyrusOne DFW10 Whitney / Thad Hill Powered Land use?
CyrusOne DFW10 Whitney / Thad Hill Powered Land has 0.40 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building CyrusOne DFW10 Whitney / Thad Hill Powered Land?
CyrusOne is recorded as a party to CyrusOne DFW10 Whitney / Thad Hill Powered Land on the DEPLOY registry. The full party list, with each role, is on the record.
Is CyrusOne DFW10 Whitney / Thad Hill Powered Land operating yet?
As of the most recent verification on the DEPLOY registry, CyrusOne DFW10 Whitney / Thad Hill Powered Land is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on CyrusOne DFW10 Whitney / Thad Hill Powered Land?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track CyrusOne DFW10 Whitney / Thad Hill Powered Land on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). CyrusOne DFW10 Whitney / Thad Hill Powered Land: AI data center campus record. Retrieved October 2, 2026, from https://registry.deploy.report/datacenters/cyrusone-dfw10-whitney-thad-hill-bosque-texas

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.