| Fluidstack Wythe County Campus | Lake Mariner Data Campus | |
|---|---|---|
| Announced capacity | not recorded | 0.75 GW |
| Energized capacity | not recorded | 0.10 GW |
| Announced-to-energized gap | not recorded | 0.65 GW |
| Lifecycle | under construction | partially energized |
| Developer | Fluidstack | TeraWulf Inc. |
| Location | Wythe, Virginia, United States | Barker, New York, United States |
| Grid | not recorded | NYISO |
| Acreage | 99 acres | not recorded |
On the map
Common questions
Which is further along, Fluidstack Wythe County Campus or Lake Mariner Data Campus?
Fluidstack Wythe County Campus is under construction; Lake Mariner Data Campus is partially energized. Energized capacity: not recorded versus 0.10 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Fluidstack Wythe County Campus and Lake Mariner Data Campus?
Fluidstack Wythe County Campus is in Wythe, Virginia, United States; Lake Mariner Data Campus is in Barker, New York, United States. Each record on DEPLOY is sourced and dated.