Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Polaris Forge 1 | Garden City Data Center | |
|---|---|---|
| Announced capacity | 1 GW | not recorded |
| Energized capacity | 0.25 GW | not recorded |
| Announced-to-energized gap | 0.75 GW | not recorded |
| Lifecycle | partially energized | energized |
| Developer | Applied Digital | Applied Digital |
| Location | Ellendale, North Dakota, United States | Garden City, Glasscock County, Texas, United States |
| Grid | MISO | not recorded |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is further along, Polaris Forge 1 or Garden City Data Center?
Polaris Forge 1 is partially energized; Garden City Data Center is energized. Energized capacity: 0.25 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Polaris Forge 1 and Garden City Data Center?
Polaris Forge 1 is in Ellendale, North Dakota, United States; Garden City Data Center is in Garden City, Glasscock County, Texas, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.