DEPLOYDatabase

Company

Applied Digital

Applied Digital is a Nasdaq-listed data center developer (ticker APLD) that started as a Bitcoin-hosting operator and pivoted, from 2023 on, into building…

Founded
2021
Status
Public

Overview

Applied Digital is a Nasdaq-listed data center developer (ticker APLD) that started as a Bitcoin-hosting operator and pivoted, from 2023 on, into building large HPC and AI campuses on the Northern Plains. Its flagship site, Polaris Forge 1 in Ellendale, North Dakota (originally the "Ellendale HPC" project), is the anchor of a 15-year lease with CoreWeave; the first 100 MW building was fully energized in November 2025 and a second building came online July 2026. The company is one of the very few pure-play AI-factory landlords at gigawatt scale outside the traditional colocation majors.

In late 2025 Applied Digital reorganized around the landlord model. It signed a roughly $5 billion, multi-hundred-megawatt AI-factory lease with an unnamed US investment-grade hyperscaler at Polaris Forge 2, crossed 1 GW of contracted capacity at Polaris Forge 3 by May 2026, and in June 2026 opened a fifth campus with a 210 MW lease at Delta Forge 2. At the same time it separated its GPU cloud business into a standalone company, ChronoScale, via a combination with EKSO announced in December 2025, so that the parent no longer sells GPU hours and does not disclose an operator-owned GPU fleet or hourly pricing.

What makes Applied Digital distinctive versus the rest of the neocloud pack is that it competes on the physical layer rather than the compute layer. It sits closer to QTS, Vantage or DataBank than to CoreWeave or Nebius: hyperscaler-grade liquid-cooled shells, financed with senior secured notes (a $2.35 billion issue in November 2025 and a $1.59 billion issue in June 2026) and Macquarie development loans, and leased to a single anchor tenant per building on long dated terms.

Reality check

Q1 FY2027 results (company-claimed)

Revenue of $341.9M (up 322%), adjusted EBITDA of $64.4M and a $168M net loss from continuing operations.

Contracted capacity (company-claimed)

Aug 2026: About 1.41 GW leased across five campuses, worth about $36B over base terms ($86B with renewals).

Polaris Forge 1 (company-claimed)

Oct 2026: 250 MW operating in Ellendale, ND, fully leased to CoreWeave on 15-year terms, with 400 MW at full build-out.

Finland (company-claimed)

Oct 2026: Access to up to 1 GW of potential power in Finland, its first non-US site, from 2028. No tenant yet.

Verified record

Verified deployments
None on file
Active incidents
None on file

Key facts

Positioning

An AI data center landlord. Its GPU cloud was spun out as ChronoScale, completed May 2026.

Polaris Forge 2

An approximately $5B lease with an unnamed investment-grade hyperscaler (Oct 2025).

Polaris Forge 3 and Delta Forge 2 (2026)

Polaris Forge 3 passed 1 GW contracted in May; a 210 MW lease at Delta Forge 2 added a fifth campus in June.

Financing

$2.35B and $1.59B of secured notes, a $550M revolver and Macquarie development loans; $6.4B of debt and $3.7B of cash at Aug 31 2026.

Capacity still to be financed (reported)

CEO Wes Cummins said on November 2 that about 600 MW of the 1.4 GW plan is financed and about 800 MW still needs financing over the next 12 months.

Data & sources

Press releases

7

Web sources

6

13 sources backing this record.View all →

Partnerships

Every company Applied Digital has built with, alongside the ones only announced in a press release.

2 total2 just announced

Most-frequent partners

  1. 1CoreWeave1× joint9 total
  2. 2Soluna Holdings, Inc.1× joint1 total

Relationships

Current leadership (5)

Founders (2)

See all founders across the registry →

Safety record

No incidents on record for Applied Digital.

Only active incidents are counted. Retracted incidents are excluded from this summary but remain reachable at their canonical URLs.

Full safety record: incidents, sourcing, and exposure data →

Applied Digital on the data-center map

Every verified data center Applied Digital operates that has a mapped coordinate (19 total). Filled circles are Tier-2 facilities and Tier-1 campuses under this operator; click any pin to open its record.

Applied Digital data centers (19)

AI data centers Applied Digital operates or is a party to, from the DEPLOY data center registry.

Recent coverage

Applied Digital in third-party press

Mentioned on (3)

Registry pages whose text names Applied Digital.

Companies (1)

ChronoScale