Data center campus
Delta Forge 1 (Boyce / Rapides Parish)
Delta Forge 1 is an AI data center campus developed by Applied Digital in Louisiana, Rapides Parish. 0.30 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Applied Digital · Private land · other · Boyce, Rapides Parish, Louisiana, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.30 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Expected online: July 1, 2027. 7 months away..
| Source | ||||
|---|---|---|---|---|
| Announced | 0.30 GW | 2026-05-26 | reported | government |
| Contracted | 0.30 GW | 2026-04-23 | reported | sec filing |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Operator / developer
- Applied Digital (designs, builds, operates)
- Location
- Boyce, Rapides Parish, Louisiana; first Applied Digital Louisiana campus
- Timeline
- Groundbreaking announced Jan 22 2026; initial operations targeted mid-2027
- Power (company-claimed)
- 430 MW utility power enabling up to 300 MW critical IT across two 150 MW facilities
- Hyperscaler lease (company-claimed)
- 300 MW critical IT on a ~15-year lease with an unnamed US hyperscaler; about $7.5B contract value
- Site size (sources differ)
- More than 500 acres per Applied Digital; about 300 acres for first two buildings per state
- Serving utility
- Cleco
- Cooling (company-claimed)
- Proprietary waterless, closed-loop cooling for high-density AI
- Stated investment
- $3.6 billion per Louisiana Economic Development
- Jobs
- 200 full-time jobs; 1,000+ peak construction workers
- State incentive
- Sales and use tax exemption on data center equipment under Act 730 (2024)
- Related campus
- Distinct from Delta Forge 2 in Ellendale, ND
On the data center map
Every tracked data center is on this map, centered on Delta Forge 1. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Announced capex
- $3.6B
- Jobs
- 200 permanent reported
- Cooling
- closed-loop / waterless (company proprietary)
- Grid
- other · live in ~10 months
- Tenant
- Unnamed U.S. high investment-grade hyperscaler
- Cost per MW
- $12M/MW
- Cost per job
- $18M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterRapides Parish(3)·Louisiana(26)
The deal
- developer
- Applied Digital · Designs, builds, and operates the Delta Forge 1 AI Factory campus.
- utility
- Cleco · Named power supplier in the Louisiana Economic Development announcement.
- tenant
- Unnamed U.S. high investment-grade hyperscaler · April 23, 2026 lease for 300 MW critical IT (~$7.5B / ~15-year term). Company does not name the counterparty.
Power
- Power source
- grid
- Grid operator
- other
- Interconnection
- Water
- Applied Digital describes proprietary waterless / closed-loop cooling for high-density AI halls ([Applied Digital IR](https://ir.applieddigital.com/news-events/press-releases/detail/144/applied-digital-breaks-ground-on-delta-forge-1-a-430-mw-ai); [Louisiana Economic Development](https://www.opportunitylouisiana.gov/news/central-louisiana-secures-3-6-billion-applied-digital-ai-factory-campus)).
County water status: Exceptional drought (D4) in Rapides Parish, week of 2026-11-10 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Delta Forge 1 sits on private land in Louisiana, Rapides Parish. It connects to the other grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- LED-framed campus investment
- $3.6B. Louisiana Economic Development framing of a $3.6B Applied Digital AI factory campus investment. government
- Hyperscaler lease at Delta Forge 1 (300 MW critical IT)
- $7.5B. Company: approximately $7.5B total contracted value over an estimated 15-year base term covering 300 MW critical IT; tenant unnamed U.S. high investment-grade hyperscaler. sec filing
Regulatory paper trail
The permits, filings and rules on record for this site and its jurisdiction. Each is a sourced, dated artifact you can follow to the primary document. 1 permit on file with LDEQ: 1 air permit (1 pending).
Investment, workforce and specs
Timeline
- Nov 2026permit recordedAir permit (proposed initial synthetic minor source operating permit) 2360-00175-00 recorded from https://deq.louisiana.gov/public-notices?pn=12
- Nov 2026Current: Under construction
Sources
- Applied Digital Breaks Ground on Delta Forge 1, a 430 MW AI Factory Campus in a Southern U.S. State · Applied Digital IR
- Central Louisiana Secures $3.6 Billion Applied Digital AI Factory Campus · Louisiana Economic Development
- Applied Digital Form 8-K (Apr 23, 2026) — Delta Forge 1 hyperscaler lease · SEC Form 8-K / Applied Digital
8ad2dfad-c906-4d69-bfb9-b9d78a8671c3 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Delta Forge 1 (Boyce / Rapides Parish)?
How much power will Delta Forge 1 (Boyce / Rapides Parish) use?
Who is building Delta Forge 1 (Boyce / Rapides Parish)?
Is Delta Forge 1 (Boyce / Rapides Parish) operating yet?
How verified is the data on Delta Forge 1 (Boyce / Rapides Parish)?
Deploy Watch
Track Delta Forge 1 (Boyce / Rapides Parish) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Delta Forge 1 (Boyce / Rapides Parish): AI data center campus record. Retrieved November 20, 2026, from https://registry.deploy.report/datacenters/applied-digital-delta-forge-1-boyce-louisiana
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/applied-digital-delta-forge-1-boyce-louisiana.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/applied-digital-delta-forge-1-boyce-louisiana
- Data documentation: /data
- Query this programmatically: Deploy MCP