Data center comparison
Delta Forge 1 vs Delta Forge 2
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Delta Forge 1 | Delta Forge 2 | |
|---|---|---|
| Announced capacity | 0.30 GW | not recorded |
| Energized capacity | not recorded | not recorded |
| Announced-to-energized gap | 0.30 GW | not recorded |
| Lifecycle | under construction | announced |
| Developer | Applied Digital | Applied Digital |
| Location | Boyce, Rapides Parish, Louisiana, United States | Brookwood, Tuscaloosa, Alabama, United States |
| Grid | other | not recorded |
| Acreage | 500 acres | not recorded |
On the map
Common questions
Which is further along, Delta Forge 1 or Delta Forge 2?
Delta Forge 1 is under construction; Delta Forge 2 is announced. Energized capacity: not recorded versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Delta Forge 1 and Delta Forge 2?
Delta Forge 1 is in Boyce, Rapides Parish, Louisiana, United States; Delta Forge 2 is in Brookwood, Tuscaloosa, Alabama, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.