DEPLOYDatabase

Data center comparison

EdgeCore Reno Data Center Campus vs Switch Citadel Campus

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

EdgeCore Reno Data Center CampusSwitch Citadel Campus
Announced capacity0.22 GW0.65 GW
Energized capacitynot recorded0.13 GW
Announced-to-energized gap0.22 GW0.52 GW
Lifecyclepartially energizedpartially energized
DeveloperEdgeCore Digital InfrastructureSwitch, Inc.
LocationReno, Nevada, United StatesMcCarran (Tahoe Reno Industrial Center), Nevada, United States
Gridnot recordedWECC
Acreage56 acres2,000 acres

On the map

Common questions

Which is bigger, EdgeCore Reno Data Center Campus or Switch Citadel Campus?
By announced capacity, Switch Citadel Campus is larger: 0.65 GW versus 0.22 GW. Announced figures are claims, not built capacity.
Which is further along, EdgeCore Reno Data Center Campus or Switch Citadel Campus?
EdgeCore Reno Data Center Campus is partially energized; Switch Citadel Campus is partially energized. Energized capacity: not recorded versus 0.13 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are EdgeCore Reno Data Center Campus and Switch Citadel Campus?
EdgeCore Reno Data Center Campus is in Reno, Nevada, United States; Switch Citadel Campus is in McCarran (Tahoe Reno Industrial Center), Nevada, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.