Data center campus
Switch Citadel Campus (Tahoe Reno)
Switch Citadel Campus is an announced AI data center campus. 0.65 GW of capacity has been announced; 0.13 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Private land · McCarran (Tahoe Reno Industrial Center), Nevada, United States
Capacity: announced vs energized
Announced
0.65 GW
claimed
Contracted
not recorded
Under construction
not recorded
Energized
0.13 GW
reported
Announced-to-energized gap: 0.52 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.65 GW | 2019-01-01 | claimed | press release |
| Energized | 0.13 GW | 2019-01-01 | reported | journalist report |
The deal
- developer
- Switch, Inc. · Founded/led by Rob Roy
- operator
- Switch, Inc.
- financier
- IFM Investors · Co-owner alongside DigitalBridge
- utility
- NV Energy · Switch litigated utility exit at Nevada PUC
- financier
- DigitalBridge · Took Switch private in 2022
Power
- Power source
- grid
- Interconnection
Sources
- Switch TAHOE RENO Now Open: Largest Data Center Campus in the World
- Switch, Inc. Form 8-K investor presentation (FY2018)
- Switch Launches Its First Enormous Reno Data Center
385f1c8a-eb14-4741-8526-9cab49bac9cb · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.