Data center comparison
Switch Citadel Campus vs Voltage Park Reno
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| Switch Citadel Campus | Voltage Park Reno | |
|---|---|---|
| Announced capacity | 0.65 GW | not recorded |
| Energized capacity | 0.13 GW | not recorded |
| Announced-to-energized gap | 0.52 GW | not recorded |
| Lifecycle | partially energized | energized |
| Developer | Switch, Inc. | Voltage Park |
| Location | McCarran (Tahoe Reno Industrial Center), Nevada, United States | McCarran (Tahoe Reno Industrial Center), Nevada, United States |
| Grid | WECC | not recorded |
| Acreage | 2,000 acres | not recorded |
Common questions
Which is further along, Switch Citadel Campus or Voltage Park Reno?
Switch Citadel Campus is partially energized; Voltage Park Reno is energized. Energized capacity: 0.13 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Switch Citadel Campus and Voltage Park Reno?
Switch Citadel Campus is in McCarran (Tahoe Reno Industrial Center), Nevada, United States; Voltage Park Reno is in McCarran (Tahoe Reno Industrial Center), Nevada, United States. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.