Meta Los Lunas Data Center Campus vs Stargate Doña Ana County / Project Jupiter

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Meta Los Lunas Data Center CampusStargate Doña Ana County / Project Jupiter
Announced capacitynot recorded2.20 GW
Energized capacity0.04 GW0 GW
Announced-to-energized gapnot recorded2.20 GW
Lifecyclepartially energizedunder construction
DeveloperMetaSTACK Infrastructure
LocationLos Lunas, Valencia County, New Mexico, United StatesSanta Teresa, New Mexico, United States
GridWECCWECC
Acreage750 acres1,400 acres

On the map

Common questions

Which is further along, Meta Los Lunas Data Center Campus or Stargate Doña Ana County / Project Jupiter?
Meta Los Lunas Data Center Campus is partially energized; Stargate Doña Ana County / Project Jupiter is under construction. Energized capacity: 0.04 GW versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Meta Los Lunas Data Center Campus and Stargate Doña Ana County / Project Jupiter?
Meta Los Lunas Data Center Campus is in Los Lunas, Valencia County, New Mexico, United States; Stargate Doña Ana County / Project Jupiter is in Santa Teresa, New Mexico, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.