DEPLOYDatabase

Data center comparison

Microsoft Fairwater Atlanta / QTS Fayetteville Campus vs OpenAI Project Camellia

Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

Microsoft Fairwater Atlanta / QTS Fayetteville CampusOpenAI Project Camellia
Announced capacity1.50 GWnot recorded
Energized capacity0.34 GWnot recorded
Announced-to-energized gap1.16 GWnot recorded
Lifecyclepartially energizedannounced
DeveloperMicrosoftOpenAI
LocationFayetteville, Georgia, United StatesEffingham, Georgia, United States
Gridothernot recorded
Acreage615 acresnot recorded

On the map

Common questions

Which is further along, Microsoft Fairwater Atlanta / QTS Fayetteville Campus or OpenAI Project Camellia?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is partially energized; OpenAI Project Camellia is announced. Energized capacity: 0.34 GW versus not recorded. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are Microsoft Fairwater Atlanta / QTS Fayetteville Campus and OpenAI Project Camellia?
Microsoft Fairwater Atlanta / QTS Fayetteville Campus is in Fayetteville, Georgia, United States; OpenAI Project Camellia is in Effingham, Georgia, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.