OpenAI Project Camellia vs Stargate UAE
Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.
Side by side
| OpenAI Project Camellia | Stargate UAE | |
|---|---|---|
| Announced capacity | not recorded | 1 GW |
| Energized capacity | not recorded | 0 GW |
| Announced-to-energized gap | not recorded | 1 GW |
| Lifecycle | announced | under construction |
| Developer | OpenAI | Khazna Data Centres (G42) |
| Location | Effingham, Georgia, United States | Abu Dhabi, UAE, United Arab Emirates |
| Grid | not recorded | EWEC (Emirates Water and Electricity Company) |
| Acreage | not recorded | not recorded |
On the map
Common questions
Which is further along, OpenAI Project Camellia or Stargate UAE?
OpenAI Project Camellia is announced; Stargate UAE is under construction. Energized capacity: not recorded versus 0 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are OpenAI Project Camellia and Stargate UAE?
OpenAI Project Camellia is in Effingham, Georgia, United States; Stargate UAE is in Abu Dhabi, UAE, United Arab Emirates. Each record on DEPLOY is sourced and dated.
Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.