DEPLOYDatabase

Data center campus

Stargate UAE

Stargate UAE is an announced AI data center campus. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Private land · EWEC (Emirates Water and Electricity Company) · Abu Dhabi, Abu Dhabi, United Arab Emirates


Capacity: announced vs energized

Announced
1 GW
claimed
Contracted
not recorded
Under construction
0.20 GW
reported
Energized
0 GW
reported

Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Stargate UAE capacity claims
Source
Announced1 GW2025-10-13claimedpress release
Energized0 GW2026-08-17reportedpress release
Under construction0.20 GW2025-10-13reportedpress release

The deal

developer
Khazna Data Centres (G42) · G42 subsidiary building and operating the cluster.
tenant
OpenAI · Anchor tenant; first international Stargate node.
chip supplier
Nvidia · ~100,000 GB300 Grace Blackwell chips in first 200MW.
investor
Oracle, SoftBank, Cisco · Named global partners in the Stargate UAE alliance.

Power

Power source
mixed
Grid operator
EWEC (Emirates Water and Electricity Company)
Interconnection

Financial structure

Reported total Stargate UAE / UAE-US AI Campus investment
$30B. Aggregate figure widely reported for the ~5GW campus; not itemized in G42 construction update. journalist report

Sources

49b3f935-bec2-46b6-9958-1d30f62fee79 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.