Data center campus
Stargate Norway (Kvandal / Narvik)
Stargate Norway is an announced AI data center campus. 0.23 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · greenfield · Narvik, Nordland, Norway
Capacity: announced vs energized
Announced-to-energized gap: 0.23 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.23 GW | 2025-07-31 | reported | press release |
| Announced | 0.29 GW | 2025-07-31 | claimed | press release |
| Energized | 0 GW | 2025-07-31 | reported | press release |
| Under construction | 0.02 GW | 2025-07-31 | reported | press release |
The deal
- developer
- Nscale · Designs and builds the facility; 50% co-owner via wholly owned subsidiary
- financier
- Aker ASA · 50% co-owner; industrial partner
- offtaker
- OpenAI · Initial offtaker with option to scale under OpenAI for Countries
- chip supplier
- NVIDIA · GPU supplier (100,000 GPUs targeted)
Power
- Power source
- grid
- Interconnection
Regional surplus hydropower supply, grid interconnect, Announced. Facility to run entirely on renewable hydropower; specific dedicated project capacity not disclosed
Financial structure
- Equity in initial phase (100% basis, split equally)
- $250M. Upwards of USD 250M; each partner contributes equally press release
- Committed to initial 20MW phase (both partners)
- $1B. Initial 20MW phase only press release
Sources
- Nscale, Aker and OpenAI to establish Stargate Norway
- Introducing Stargate Norway
- OpenAI partners with Nscale and Aker for Stargate Norway data center with 100k GPUs
30c92b75-7001-4e3c-b579-91a4de785cd9 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.