Overview
Nscale is a London-founded neocloud that has rocketed from a 2024 spinout of Norwegian bitcoin-mining group Arkon Energy into one of the most heavily capitalised GPU-cloud operators in Europe. Founded by Josh Payne and Nathan Townsend, it raised roughly $3.7 billion across four rounds in eighteen months, culminating in a March 2026 Series C reported at a $14.6 billion valuation with Nvidia, Nokia, Dell and Aker ASA among its strategic backers. Its distinguishing bet is vertical integration: Nscale owns land, power and buildings on cold, cheap hydro-powered sites in the Nordics (Glomfjord and Narvik in Norway, plus partner capacity in Iceland) while assembling UK and US campuses aimed at sovereign and hyperscale AI workloads.
The company's growth has been driven almost entirely by two anchor contracts. It is supplying roughly 200,000 Nvidia GPUs to Microsoft under a multi-site deal spanning Norway, Texas and Portugal, and it is Nvidia and OpenAI's chosen partner for a UK "Stargate"-style buildout at a former coal plant in Northumberland. Jensen Huang has publicly said Nscale will have around 300,000 GPUs online by the end of 2026, a scale that puts it in the same tier as CoreWeave, Crusoe and Lambda despite its youth.
Nscale positions itself as a full-stack training-and-inference cloud rather than a pure bare-metal seller: managed Slurm and Kubernetes, an inference endpoint product, and a "Radar" fleet-observability API sit on top of the raw H100/H200/B200 supply. Growth has come by acquisition as well as ground-up build, including the Monarch Compute Campus in West Virginia and a reported acquisition of Anyscale to fold in a distributed-training software layer.
Reality check
Contracted business (company-claimed)
Aug 2026 S-1: $103.4B of active and contracted value; about 461,000 GPUs and 1.37 GW, on contracts averaging about 5.7 years.
Anthropic agreements (company-claimed)
Aug 2026 S-1: GPU agreements worth up to about $44.6B for Vera Rubin capacity at Monarch Compute Campus; financing not yet committed.
ByteDance revenue share (company-claimed)
A ByteDance unit was about 73% of 2025 revenue (~$24M of $33M), on 2,304 B200 GPUs in Glomfjord, Norway.
Build commitments (company-claimed)
Jun 2026 S-1: $24.0B of equipment and $3.5B of construction commitments, plus $1.4B of leases not yet started.
Deployments (company-claimed)
Oct 2026: 50,000+ GPUs across six data centers in five countries. Ward County, Texas went live, leasing 234 MW from Ionic Digital.
Loughton grid delay (company-claimed)
The planned 90 MW Loughton, Essex site may not get a grid connection until the early-to-mid 2030s, versus a 2027 target.
New COO (company-claimed)
Justin Osofsky, 18 years at Meta (most recently Chief Partnerships Officer), joined as COO.
Verified record
- Verified deployments
- None on file
- Active incidents
- None on file
Key facts
Origin
Funding before IPO
Valuation (Mar 2026)
Pre-IPO notes (company-stated, Sep 2026)
IPO filing (Sep 2026)
Microsoft contract
Sites
UK projects
Acquisitions
Hardware and design
IPO target (reported, Sep 2026)
Capacity built (reported, Oct 2026)
Glomfjord delays (reported, Oct 2026)
Glomfjord safety inspection (reported)
Microsoft exits Loughton (reported, Oct 2026)
Loughton response (company-stated, Oct 2026)
IPO valuation pushback (reported, Oct 2026)
Second Anthropic deal talks (reported, Oct 2026)
DSX MaxLPS test (company-run, Oct 2026)
IPO pushed back (reported, Oct 2026)
Anthropic S-1 terms (counterparty filing, Oct 2026)
Nvidia credit support talks (reported, Oct 2026)
Bond market access (reported, Oct 2026)
Microsoft declined Texas expansion option (reported)
First NVIDIA Vera Rubin NVL72 systems online (company-stated)
Data & sources
Company filings
2
Press releases
1
News coverage
7
Web sources
45
55 sources backing this record.View all →
Partnerships
Every company Nscale has built with, alongside the ones only announced in a press release.
Most-frequent partners
Most recent
Relationships
Current leadership (7)
- Josh Payne Co-founder and CEOreported, not verified
- Nathan Townsend Co-founderreported, not verified
- Nidhi Chappell President, AI Infrastructurereported, not verified
- Sam Huckaby President, Data Centersreported, not verified
- David Power CTOreported, not verified
- Alice Takhtajan CFOreported, not verified
- Tom Burke CROreported, not verified
Founders (1)
- Josh Paynesole
Safety record
No incidents on record for Nscale.
Only active incidents are counted. Retracted incidents are excluded from this summary but remain reachable at their canonical URLs.
Full safety record: incidents, sourcing, and exposure data →
Nscale on the data-center map
Every verified data center Nscale operates that has a mapped coordinate (10 total). Filled circles are Tier-2 facilities and Tier-1 campuses under this operator; click any pin to open its record.
Nscale data centers (13)
- BT-owned UK sitesMultiple, Global · announced
- Loughton IILoughton · announced
- Monarch Compute CampusWharncliffe · announced
- NarvikNarvik · energized
- NorthumberlandNorthumberland · announced
- Nscale Barstow AI Data CenterBarstow · under construction
- Nscale Cobalt ParkNewcastle upon Tyne · announced
- Nscale Loughton AI Data CentreLoughton · permitted
- Stargate NorwayNarvik · under construction
- Monarch Compute CampusPoint Pleasant · planned
- Nscale Cedarvale Data Center (Ionic Digital lease)Barstow · under construction
- Nscale Monarch Compute Campus (Point Pleasant)Point Pleasant · under construction
- Nscale NC-1 (WhiteFiber/Bit Digital, Madison)Madison · 40 MW
AI data centers Nscale operates or is a party to, from the DEPLOY data center registry.
Recent coverage
Nscale in third-party press
Mentioned on (7)
Registry pages whose text names Nscale.
Financial state
- Total funding
- $3.7B
- Reporting period
- 2026-01-01 to 2026-09-30
- Reporting basis
- sec_s1
- Revenue disclosed
- $307500000 (sec_s1)
- SEC filing
- S-1
Each numeric field carries its own basis marker. Aggregators report a number; this surface preserves the source class so verification depth travels with the value.
Partnerships
3 total · 1 operating · 1 just announced
Every company Nscale has built with, alongside the ones only announced in a press release.
Most recent
All 3 partnerships
open in the atlas →- Nscale x AWSwithAWS30technology—inferred
- development2026-11-16announcedjust announced
- other2026-10-26announcedoperating
Funding rounds (3)
Nscale’s 3 disclosed rounds, $4.6B in total, oldest to newest.
- Pre-IPO convertible notes (Sep 2026)2026-09-25
$3.4B
- Series B2025-09-25
$1.1B
Investors: Aker ASA (lead), Sandton Capital Partners, Blue Owl Capital, Fidelity Management & Research Company, G Squared, Nokia (strategic), Nvidia (strategic), T.Capital
- Series A2024-12-09
$155M
Investors: Blue Sky Capital Managers, Sandton Capital Partners (lead), Kestrel 0x1, Florence Capital
Recent activity
Every change to this record is dated, sourced, and independently verified where marked.
- Record createdAug 19, 2026
Added to the verified registry
Sources (55)
- https://en.wikipedia.org/wiki/Nscale
- https://www.nscale.com/about
- https://www.nscale.com/
- https://www.nscale.com/blog
- https://www.nscale.com/press-releases/nscale-microsoft-2025 · 2025-10-15
- https://www.prnewswire.com/news-releases/nscale-files-registration-statement-for-proposed-initial-public-offering-302883591.html
- https://www.cnbc.com/2026/09/18/nscale-ai-cloud-provider-ipo-nscl.html
- https://www.sec.gov/Archives/edgar/data/2110365/000119312526395475/ck0002110365-20260918.htm · 2026-09-18
- https://x.com/RHouseResearch/status/2102843776578273456 · 2026-09-23
- https://thenextweb.com/news/nscale-bytedance-biggest-customer-nvidia-b200-norway · 2026-09-23
- https://www.tomshardware.com/tech-industry/data-centers/filing-reveals-how-bytedance-gained-access-to-over-2-000-nvidia-b200-chips-through-nscales-norway-data-center-singaporean-subsidiary-spring-contributed-73-percent-of-uk-neoclouds-2025-revenue · 2026-09-24
- https://x.com/RHouseResearch/status/2103197868538449958 · 2026-09-24
- https://www.prnewswire.com/news-releases/nscale-raises-3-36b-in-pre-ipo-convertible-financing-302890199.html · 2026-09-25
- https://www.theguardian.com/technology/2026/sep/24/construction-largest-supercomputer-delayed · 2026-09-24
- https://datacentrereview.com/2026/07/nscales-2bn-essex-data-centre-hit-by-grid-delays/ · 2026-07-14
- https://x.com/thecapitalatlas/status/2105811703308906532 · 2026-10-01
- https://www.prnewswire.com/news-releases/nscale-appoints-tech-industry-veteran-justin-osofsky-as-chief-operating-officer-302897440.html · 2026-10-02
- https://economictimes.indiatimes.com/tech/technology/nscale-hires-metas-justin-osofsky-to-be-coo-ahead-of-ipo/articleshow/134658315.cms · 2026-10-02
- https://www.techradar.com/pro/nvidia-backed-neocloud-nscale-faces-years-of-delay-because-uks-largest-ai-supercomputer-cant-get-enough-power-from-the-grid-to-feed-its-data-centers
- https://www.euronews.com/2026/09/29/uks-biggest-ai-supercomputer-may-have-to-wait-until-2030s-for-enough-power · 2026-09-29
- https://www.themorningintelligence.uk/nscale-data-centre-loughton-essex-delayed-2030s-power/ · 2026-09-24
- https://www.nscale.com/press-releases/execution-at-scale · 2026-10-01
- https://www.nasdaq.com/press-release/ionic-digital-announces-second-quarter-2026-results-2026-08-19 · 2026-08-19
- https://colocationscout.com/news-nscale-ward-county-live-ionic-lease-terms.html · 2026-10-06
- https://x.com/ColocationScout/status/2107526559183642976 · 2026-10-06
- https://www.nscale.com/press-releases/ai-hyperscaler-nscale-secures-usd-155-million-in-series-a · 2024-12-09
- https://www.nscale.com/press-releases/nscale-series-b · 2025-09-25
- https://finance.yahoo.com/technology/ai/articles/nvidia-backed-data-center-firm-195220456.html · 2026-09-18
- https://www.cityam.com/nscale-files-for-35bn-us-listing/ · 2026-09-20
- https://www.bloomberg.com/news/features/2026-10-15/nscale-s-35-billion-ipo-plans-muddied-by-ai-data-center-delays · 2026-10-15
- https://energiteknikk.net/2026/06/dsb-fant-ti-avvik-hos-ki-datasenter-i-glomfjord/ · 2026-06-01
- https://www.telegraph.co.uk/business/2026/10/18/microsoft-axes-ai-deal-setback-uk-data-centre-pioneer/ · 2026-10-18
- https://www.theguardian.com/uk-news/2026/oct/18/microsoft-drops-huge-ai-datacentre-project-in-essex-over-power-supply-concerns · 2026-10-18
- https://www.ft.com/content/35cc5cc6-f9b6-49cc-8fc2-bd61e09c8c40 · 2026-10-18
- https://www.investing.com/news/stock-market-news/microsoft-pulls-out-of-uk-data-center-deal-with-nscale-telegraph-reports-4955864 · 2026-10-18
- https://www.businessday.co.za/world/international-companies/2026-10-18-microsoft-pulls-out-of-uk-data-centre-project/ · 2026-10-18
- https://www.bloomberg.com/news/articles/2026-10-18/microsoft-scraps-uk-data-center-deal-with-nscale-telegraph-says · 2026-10-18
- https://news.bloomberglaw.com/securities-law/ai-cloud-firm-nscale-faces-investor-pushback-over-ipo-valuation · 2026-10-18
- https://www.businesstimes.com.sg/companies-markets/ai-cloud-firm-nscale-faces-investor-pushback-over-ipo-valuation · 2026-10-18
- https://x.com/FirstSquawk/status/2111975690035966341 · 2026-10-18
- https://news.bloomberglaw.com/capital-markets/nscale-anthropic-in-talks-for-45-billion-cloud-computing-deal · 2026-10-19
- https://www.investing.com/news/stock-market-news/nscale-anthropic-in-talks-for-45-billion-cloud-computing-deal-bloomberg-news-reports-4958188 · 2026-10-19
- https://www.finansavisen.no/teknologi/2026/10/19/8388881/ny-milliardavtale-anthropic-i-storforhandlinger-med-nscale · 2026-10-19
- https://nvidianews.nvidia.com/news/european-ecosystem-builds-worlds-most-efficient-ai-factories-with-nvidia-dsx · 2026-10-21
- https://www.channelnewsasia.com/business/analysisanthropic-ipo-stands-alone-ai-market-jitters-sideline-others-6482816 · 2026-10-22
- https://www.sec.gov/Archives/edgar/data/2130357/000162828026067168/anthropicpbc-sx1.htm · 2026-10-26
- https://www.theinformation.com/articles/nvidia-talks-provide-billions-credit-support-cloud-providers-45-billion-anthropic-deal · 2026-10-29
- https://www.channelnewsasia.com/business/nvidia-in-talks-give-credit-support-nscales-deal-anthropic-information-reports-6505526 · 2026-10-29
- https://x.com/i/trending/2115948146949837116 · 2026-10-29
- https://www.wsj.com/finance/the-new-bottleneck-in-americas-ai-build-out-a-shortage-of-cheap-money-0c14c84d · 2026-10-31
- https://aiweekly.co/alerts/wsj-coreweave-nebius-and-nscale-effectively-shut-out-of-bond-market-as-lenders · 2026-10-31
- https://pivotnews.ai/five/bond-market-closes-to-coreweave-nebius-and-nscale-wsj · 2026-10-31
- Microsoft declines option to expand Texas data center deal with Nscale, source says · https://www.reuters.com/5f374b32b07b/technology/microsoft-rejects-multibillion-dollar-ai-deal-with-uks-nscale-ft-reports-2026-11-05/ · 2026-11-05
- Microsoft Declines Nscale Compute Option Worth Billions · https://www.silicon.co.uk/cloud/datacenter/microsoft-nscale-texas-632212 · 2026-11-09
- Nscale deploys its first NVIDIA Vera Rubin NVL72 AI supercomputers · https://www.nscale.com/press-releases/nscale-first-nvidia-vera-rubin-nvl72-deployment · 2026-11-18
Common questions
What is Nscale?
What does Nscale make?
Is Nscale publicly traded?
Who is the CEO of Nscale?
How can I invest in Nscale?
Where is Nscale headquartered?
How much funding has Nscale raised?
Who owns Nscale?
Is Nscale a top robotics company?
When was Nscale founded?
Is Nscale safe?
Methodology: Verified · 55 sources (3 primary) · last reviewed 2026-11-20
Verification posture
Verified
High confidence
Review state
Stable
Last reviewed 2026-11-20
Sources by quality tier
- 44
- unclassified
- Unclassified source
- 6
- secondary-established-publication
- Established publication
- 2
- primary-sec-filing
- SEC filing
- 1
- knowledge-base
- Knowledge base
- 1
- primary-company-ir
- Company IR disclosure
- 1
- secondary-industry-publication
- Industry publication
The framework is documented at /methodology. Corrections at /corrections. Reviewer: DEPLOY editorial team.
Methodology surface for Nscale.In the press
Recent coverage mentioning Nscale from third-party publications. Automatically surfaced; not part of the verified registry record.
Figure AI plans $3.5 billion humanoid supercomputer build
Figure AI plans to train its humanoids on a large Nscale computing cluster, with initial systems scheduled to come online in the second half of 2027. The post Figure AI plans $3.5…
Nscale signs $3.5bn compute agreement with robotics company Figure
Nscale signed a $3.5 billion compute agreement with Figure AI to deploy up to 100,000 NVIDIA Vera Rubin GPUs starting H2 2027 in Barstow, TX, with Nscale also taking a strategic…
Nscale, Figure Sign $3.5B Humanoid Robot Compute Deal
Insider Brief Nscale has signed a multi-year partnership with humanoid robotics company Figure that could deploy up to 100,000 Nvidia GPUs, with an initial $3.5 billion compute…
Nscale and Figure Sign Strategic Partnership to Power the Next Generation of Physical AI
Nscale and Figure AI signed a $3.5 billion compute agreement providing up to 100,000 NVIDIA Vera Rubin GPUs for humanoid robotics training, with Nscale taking an equity stake in…
Nscale Inks $3.5 Billion Deal With Robotics Firm Figure
Nscale committed $3.5 billion in compute to Figure AI under a multi-year agreement for up to 100,000 NVIDIA Vera Rubin GPUs to train Figure's humanoid robots, taking an equity…
Nscale Backs Robot Firm Figure Alongside $3.5 Billion Cloud Deal
Bloomberg reports Nscale is backing humanoid robotics firm Figure AI with a $3.5 billion cloud compute deal for up to 100,000 NVIDIA Vera Rubin GPUs and an equity stake, as the…
Nscale and Figure Sign Strategic Partnership to Power the Next Generation of Physical AI
Nscale and Figure AI announced a strategic partnership to supply up to 100,000 NVIDIA Vera Rubin GPUs for humanoid robot AI training, described as powering the next generation of…
Figure and Nscale Sign Strategic Partnership For Up to 100,000 GPUs on the NVIDIA Vera Rubin Platform
Figure AI and Nscale announced a multi-year strategic partnership committing up to 100,000 NVIDIA Vera Rubin GPUs to power Figure's humanoid robot AI training, with Nscale also…
Machine-readable surfaces
- Markdown mirror: /companies/nscale.md
- RSS feed: /companies/nscale/feed.xml
- JSON-LD: embedded in this page’s head
- REST API: /v1/companies/51b8d117-30f7-458b-a25a-119184c9cc05
- Revision history: /companies/nscale/history
- Data documentation: /data
- Query this programmatically: Deploy MCP
Heat Index
Serious52/100
A composite of competitive footprint, funding, press velocity, active partnerships, and supply-chain edges. Different from the Intelligence score below (which is per-form-factor productization). Non-robotics companies cap at 25.
Reality vs attention
Not enough verified signal yet to place Nscale against peers. Reality and attention percentiles publish once the underlying record clears its data floor.
6-month trend
Analysis
Well-capitalized with $4.6B raised and recent funding activity. Limited public visibility and press coverage relative to peers.
Signal flags
Dimension breakdown
Verified signal
Attention (reach, not merit)
DEPLOY Intelligence scores are computed from verified registry data: confirmed deployments, disclosed funding rounds, regulatory filings, active job listings, video viewership, and press coverage. Confidence ratings reflect data availability. Scores update nightly.
DEPLOY Indices — verified vs claimed
Last computed: Nov 20, 2026
Appears in DEPLOY reports