Nscale Barstow AI Data Center is an AI data center campus developed by Nscale in Texas, Barstow. 0.70 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Nscale · ERCOT · Barstow, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.70 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q3 2026. 1 month away. Claimed by Nscale (reported) (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.20 GW | 2026-06-01 | claimed | journalist report |
| Announced | 0.70 GW | 2025-10-01 | reported | company filing |
| Contracted | 0.24 GW | 2026-06-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Nscale
Developer
Location
Grid
Announced-to-energized gap
On the data center map
Every tracked data center is on this map, centered on Nscale Barstow AI Data Center. Pan or zoom out to see how close rivals are building.
The deal
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
The Texas (ERCOT) grid demand right now: 72.1 GW (EIA-930, 2026-08-20 05:00). Nscale Barstow AI Data Center's announced 0.70 GW would be 1.0% of the grid's current load.
County water status: No drought in Ward County, week of 2026-08-11 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Nscale Barstow AI Data Center is in Texas, Barstow. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Nscale-Microsoft AI compute contract (up to)
- up to $14B. Contract value stated up to ~$14B; not campus construction cost journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Estimated compute: the claimed Approximately 104,000 NVIDIA GB300 GPUs at the Texas campus chips are on the order of 90x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
Timeline
- Aug 2026party addedchip_supplier: a9609061-00fd-4d9b-9b2d-ce2d772ab825
- Aug 2026Current: Under construction
Sources
8816a42d-177f-434d-9475-db84f39e535c · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Nscale Barstow AI Data Center (Microsoft)?
How much power will Nscale Barstow AI Data Center (Microsoft) use?
Who is building Nscale Barstow AI Data Center (Microsoft)?
Is Nscale Barstow AI Data Center (Microsoft) operating yet?
How verified is the data on Nscale Barstow AI Data Center (Microsoft)?
Deploy Watch
Track Nscale Barstow AI Data Center (Microsoft) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Nscale Barstow AI Data Center (Microsoft): AI data center campus record. Retrieved August 20, 2026, from https://registry.deploy.report/datacenters/nscale-barstow-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/nscale-barstow-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/nscale-barstow-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP