Data center campus
Nscale Barstow AI Data Center (Microsoft)
Nscale Barstow AI Data Center is an AI data center campus developed by Nscale in Texas, Barstow. 0.70 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Nscale · ERCOT · Barstow, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.70 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: Q3 2026. 0 months away. Claimed by Nscale (reported) (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 1.20 GW | 2026-06-01 | claimed | journalist report |
| Announced | 0.70 GW | 2025-10-01 | reported | company filing |
| Contracted | 0.24 GW | 2026-06-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- IT capacity (announced, platform)
- Nscale Oct 15 2025 Microsoft release: approximately 240 MW hyperscale AI campus in Texas delivering ~104,000 NVIDIA GB300 GPUs to Microsoft from Q3 2026; leased from Ionic Digital with a claimed path to 1.2 GW and Microsoft option on a further 700 MW from late 2027 (Nscale)
- Operator / tenant
- Nscale as operator supplying Microsoft; site leased from Ionic Digital per Nscale primary (Nscale)
- City naming
- Registry places this row in Barstow / Ward County from secondary coverage (Tech.eu, DCD). Nscale's Oct 2025 Microsoft release names Texas and Ionic Digital but does not itself say Barstow.
- Overlap HOLD
- Likely the same campus as nscale-texas-campus (Microsoft / Ionic Digital Texas row). Merge held: Nscale primary still does not publish a single site map proving one vs two Texas campuses; nscale-texas-campus also currently points at an unrelated Corpus Christi location stub that needs steward cleanup before any merge.
On the data center map
Every tracked data center is on this map, centered on Nscale Barstow AI Data Center. Pan or zoom out to see how close rivals are building.
- Announced capex
- $14B
- GPUs
- 104K Approximately 104,000 NVIDIA GB300 GPUs at the Texas campus
- Tenant
- Microsoft
- Land owner
- Ionic Digital
- Cost per MW
- $20M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterTexas(606)
The deal
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
The Texas (ERCOT) grid demand right now: 57.2 GW (EIA-930, 2026-10-03 16:00). Nscale Barstow AI Data Center's announced 0.70 GW would be 1.2% of the grid's current load.
County water status: Extreme drought (D3) in Ward County, week of 2026-09-29 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Nscale Barstow AI Data Center is in Texas, Barstow. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Nscale-Microsoft AI compute contract (up to)
- up to $14B. Contract value stated up to ~$14B; not campus construction cost journalist report
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Estimated compute: the claimed Approximately 104,000 NVIDIA GB300 GPUs at the Texas campus chips are on the order of 90x the compute used to train a GPT-4-class model. Derived from the chip-count claim, not measured (basis).
Timeline
- Aug 2026party linkedoperator: linked externalName "Nscale" to company nscale
- Oct 2026Current: Under construction
Sources
- Tech.eu: Nscale US site and Microsoft compute deal
- DCD: Nscale to supply Microsoft with Nvidia GPUs
- Nscale Contracts ~200,000 NVIDIA GB300 GPUs with Microsoft
8816a42d-177f-434d-9475-db84f39e535c · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Nscale Barstow AI Data Center (Microsoft)?
How much power will Nscale Barstow AI Data Center (Microsoft) use?
Who is building Nscale Barstow AI Data Center (Microsoft)?
Is Nscale Barstow AI Data Center (Microsoft) operating yet?
How verified is the data on Nscale Barstow AI Data Center (Microsoft)?
Deploy Watch
Track Nscale Barstow AI Data Center (Microsoft) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Nscale Barstow AI Data Center (Microsoft): AI data center campus record. Retrieved October 4, 2026, from https://registry.deploy.report/datacenters/nscale-barstow-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/nscale-barstow-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/nscale-barstow-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP