Announced-vs-energized capacity, lifecycle, developer, and location for two AI data center campuses, side by side and individually sourced.


Side by side

xAI Colossus 2 Data CenterxAI Colossus
Announced capacity1.20 GW2 GW
Energized capacitynot recorded1 GW
Announced-to-energized gap1.20 GW1 GW
Lifecyclepartially energizedpartially energized
DeveloperxAIxAI
LocationSouthaven, Mississippi, United StatesMemphis, Tennessee, United States
Gridnot recordednot recorded
Acreagenot recordednot recorded

On the map

Common questions

Which is bigger, xAI Colossus 2 Data Center or xAI Colossus?
By announced capacity, xAI Colossus is larger: 2 GW versus 1.20 GW. Announced figures are claims, not built capacity.
Which is further along, xAI Colossus 2 Data Center or xAI Colossus?
xAI Colossus 2 Data Center is partially energized; xAI Colossus is partially energized. Energized capacity: not recorded versus 1 GW. DEPLOY tracks the announced-to-energized gap, so "further along" means more energized, not more announced.
Where are xAI Colossus 2 Data Center and xAI Colossus?
xAI Colossus 2 Data Center is in Southaven, Mississippi, United States; xAI Colossus is in Memphis, Tennessee, United States. Each record on DEPLOY is sourced and dated.

Compare more on the data center index or the national map. Announced numbers are claims, not built capacity; see the methodology.