DEPLOYDatabase

Data center campus

xAI Colossus 2 Data Center

xAI Colossus 2 Data Center is an AI data center campus developed by xAI in Mississippi, Southaven. 1.20 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · xAI · Southaven, Mississippi, United States


Capacity: announced vs energized

Announced-to-energized gap: 1.20 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026. 4 months away. Claimed by xAI (reported) (source).

xAI Colossus 2 Data Center capacity claims
Source
Announced1.20 GW2026-06-01reportedjournalist report

Key facts

1.20 GW

Announced

0 GW

Energized

xAI

Developer

1.20 GW

Announced-to-energized gap

On the data center map

Every tracked data center is on this map, centered on xAI Colossus 2 Data Center. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.

The deal

developer
xAI · Owner and operator of Colossus supercomputer campuses
operator
xAI

Power

Power source
behind the meter gas
Interconnection

Colossus 2 on-site gas turbine fleet, 0.49 GW gas, Partially energized. ~46 turbines (~495 MW) reported operating; 41 additional turbines permitted March 2026

County water status: No drought in DeSoto County, week of 2026-08-11 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.

Why here

xAI Colossus 2 Data Center is in Mississippi, Southaven. It draws on behind the meter gas power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Reported multi-billion investment (largest private-sector in state history)
Aggregate figures vary across reports journalist report

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

NHTSA Recall: Zoox Robotaxi Software Update for Heavy Smoke Visibility (26E044)operational restriction · 2026-07-15 · United States
FCC Proposed Fines Against Drone Companies (July 2026)other · 2026-07-10 · United States
FAA Proposed Rule: Enabling Supersonic Overland Flight (July 2026)operational restriction · 2026-07-02 · United States

Investment, workforce and specs

Timeline

  1. Aug 2026
    party added
    operator: d7bc30aa-e892-42f7-a58a-e172534fec48
  2. Aug 2026
    Current: Partially energized

Sources

1135eddf-79b2-4cde-aa07-753c2624341f · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is xAI Colossus 2 Data Center?
xAI Colossus 2 Data Center is an AI data center campus tracked on the DEPLOY registry, located in Southaven. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will xAI Colossus 2 Data Center use?
xAI Colossus 2 Data Center has 1.20 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building xAI Colossus 2 Data Center?
xAI is recorded as a party to xAI Colossus 2 Data Center on the DEPLOY registry. The full party list, with each role, is on the record.
Is xAI Colossus 2 Data Center operating yet?
As of the most recent verification on the DEPLOY registry, xAI Colossus 2 Data Center is partially energized. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on xAI Colossus 2 Data Center?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track xAI Colossus 2 Data Center on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). xAI Colossus 2 Data Center: AI data center campus record. Retrieved August 20, 2026, from https://registry.deploy.report/datacenters/xai-colossus-2-southaven-mississippi

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces