Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center

The Indiana Utility Regulatory Commission unanimously approved AES Indiana's solar, battery storage and power line plan to serve a 390-megawatt Google data center in Monrovia, the first data center filed under a 2025 state law that requires large users to cover 80% of costs assigned to them. AES estimates the investment at $1.3 billion and says Google pays all costs under a contract of at least 15 years, though the order lets existing customers carry a share of upgrade costs.

Jurisdiction: United States/Indiana/Morgan/Monrovia · Effective 2026-10-07


Machine-readable surfaces

Sources (2)

  1. Data centers · https://www.aesindiana.com/data-centers · 2026-10-07
  2. Indiana approves AES plan to power Google data center in Monrovia · https://www.wfyi.org/statewide/2026-10-12/indiana-approves-aes-plan-to-power-google-data-center-in-monrovia · 2026-10-12

Common questions

What does Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center cover?
The Indiana Utility Regulatory Commission unanimously approved AES Indiana's solar, battery storage and power line plan to serve a 390-megawatt Google data center in Monrovia, the first data center filed under a 2025 state law that requires large users to cover 80% of costs assigned to them. AES estimates the investment at $1.3 billion and says Google pays all costs under a contract of at least 15 years, though the order lets existing customers carry a share of upgrade costs.
Where does Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center apply?
Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center is recorded as a permitting requirement applying in Monrovia on the DEPLOY registry.
When did Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center take effect?
Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center is recorded as effective October 7, 2026 on the DEPLOY registry.
Is Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center still in effect?
Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center is currently in effect and applies to covered operators in the named jurisdiction.
What types of robots does Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center apply to?
Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center is recorded as cross-cutting on the DEPLOY registry, meaning it does not single out one robot form factor. Operators of any covered robot type in Monrovia should review the underlying primary sources for applicability.
Methodology: Verified · 2 sources (no primary) · last reviewed 2026-11-01

Verification posture

Verified

Low confidence

Review state

Stable

Last reviewed 2026-11-01

Sources by quality tier

2
unclassified
Unclassified source

The framework is documented at /methodology. Corrections at /corrections. Reviewer: DEPLOY editorial team.

Methodology surface for Indiana Utility Regulatory Commission approves AES Indiana plan to power Google's 390 MW Monrovia data center.

Canonical ID 54d0ab61-1b8e-4252-ab76-a3e71409c2c1