The industry uses critical IT megawatts (MW) to measure data-center size, not square footage. Below is the DEPLOY registry’s leaderboard, ranked by per-facility critical IT MW. As of 2026-08-24, 30 facilities on this list.

#FacilityOperatorWhereStatusCritical IT
1Comanche CircleSailfish Digital VenturesTexasannounced5.0 GW
2Data City, TexasEnergy Abundance Development CorporationTexasplanned5.0 GW
3Caldwell Valley Technology ParkTractTexasplanned4.0 GW
4Project Camellia (OpenAI Stargate Effingham)OpenAIGeorgiaplanned3.2 GW
5Virginia HighlandsTractSoutheastplanned2.5 GW
6Adams Fork Harless Data Center CampusTransGas Development SystemsVirginiaplanned2.5 GW
7Adams Fork Twisted Gun Data Center CampusTransGas Development SystemsVirginiaplanned2.5 GW
8Hanover Technology ParkTractVirginiaplanned2.4 GW
9Tract Hanover County Data Center Campus (Beaverdam)TractVirginiaplanned2.4 GW
10Alpha Digital CampusPowerBridge (LandBridge land partner)Texasannounced2.0 GW
11Alpha Digital CampusPowerBridge LLC / LandBridgeTexasplanned2.0 GW
12Microsoft Pecos Datacenter CampusMicrosoftTexasplanned2.0 GW
13Project BunkhouseDigital RealtyGeorgiaplanned1.8 GW
14Paducah American Energy HubNextEra Energy ResourcesKentuckyannounced1.8 GW
15PowerHouse + Provident Grand Prairie CampusPowerHouse Data Centers (with Provident)Texasunder construction1.8 GW
16PowerHouse Grand Prairie (PowerHouse/Provident DFW campus)PowerHouse Data CentersTexasunder construction1.8 GW
17PowerHouse Joliet Technology CenterPowerHouse Data CentersIllinoisplanned1.8 GW
18Tract Buckeye Data Center ParkTractSouthwestannounced1.8 GW
19Pole Canyon Technology ParkTractUtahplanned1.7 GW
20IREN Oklahoma Data CenterIRENMidwestplanned1.6 GW
21Beale Marana CampusBeale InfrastructureArizonaplanned1.5 GW
22Core Scientific Pecos Campus ExpansionCore ScientificTexasunder construction1.5 GW
23Red Butte Energy and Data Center CampusBrightNightUtahplanned1.5 GW
24South Dallas OneGridFree AITexasplanned1.5 GW
25Alterra Marshall Data Center (Brooks Industrial Park)Alterra DevelopmentMichiganplanned1.4 GW
26Frontier (Stargate Shackelford County campus)Vantage Data CentersTexasunder construction1.4 GW
27IREN Sweetwater 1IRENTexasunder construction1.4 GW
28Stargate Michigan Campus (Saline Township)Oracle / OpenAI / Related DigitalMichiganunder construction1.4 GW
29Sweetwater 1 Data CenterIREN LimitedTexasunder construction1.4 GW
30Vantage Frontier CampusVantage Data CentersTexasunder construction1.4 GW

Related answers

Rebuilt every 15 minutes from data_center_facilities. Critical IT MW is the industry-standard capacity number (the power actually available to compute equipment, after cooling/losses). Facilities without a disclosed MW figure are hidden from this list even when large. Announced-only capacity claims live on each facility page.