DEPLOYDatabase

Data center facility

Microsoft East Point Campus

Microsoft · East Point · 4615 Ben Hill Rd, East Point, GA 30349. Every figure below is individually sourced and dated.


In clusterFulton(3)·Georgia(160)

Facility record

under construction

Status

hyperscale

Type

Microsoft

Operator

East Point

Location

18.15 MW

Critical IT

Coweta-Fayette EMC

Serving utility

On the data center map

Free to use on your site, with a link back to DEPLOY.

Construction evidence

Dated satellite imagery of the site itself, oldest to newest. This is what the campus looks like from orbit over time, not a status we recorded: bare land, grading, and building mass tell their own story. Sentinel-2 true color, 10 m resolution, cloud-free scenes; it shows site-scale change, not fine detail. Click any frame to expand it.

2018-06-04Contains modified Copernicus Sentinel data 2018
2020-09-06Contains modified Copernicus Sentinel data 2020
2022-05-09Contains modified Copernicus Sentinel data 2022
2024-05-28Contains modified Copernicus Sentinel data 2024
2025-09-10Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. How we source and verify it: satellite construction evidence.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • criticalItMw: 18.15 (reported) · source · permit: 'critical IT load'
  • record: Microsoft East Point Campus (reported) · source
  • servingUtility: Coweta-Fayette EMC (reported) · source
  • status: under_construction (reported) · source
  • streetAddress: 4615 Ben Hill Rd, East Point, GA 30349 (reported) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Aug 2026
    Current: under construction

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Microsoft East Point Campus?
Microsoft East Point Campus is a data center facility record on the DEPLOY registry, in East Point. Every fact on the record is individually sourced and dated.
Who operates Microsoft East Point Campus?
Microsoft operates Microsoft East Point Campus, per the sourced record on the DEPLOY registry.
Is Microsoft East Point Campus operating?
Microsoft East Point Campus is recorded as under construction on the DEPLOY registry, with 18.15 MW of critical IT capacity. Each figure traces to a source.
How verified is the data on Microsoft East Point Campus?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Microsoft East Point Campus on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Microsoft East Point Campus: data center facility record. Retrieved August 24, 2026, from https://registry.deploy.report/datacenters/facilities/microsoft-east-point-ga-campus

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces