Data center facility
Meta Los Lunas Campus
Meta · Los Lunas. Every figure below is individually sourced and dated.
Part of the tracked campus Meta Los Lunas Data Center Campus.
- Announced capex
- $800M
- Jobs
- 300 permanent reported
- Cooling
- Eight completed buildings totaling ~3.8 million sq ft on ~750-acre parcel
- Cost per job
- $3M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterValencia County(4)·New Mexico(28)
The deal
Inherited from campus Meta Los Lunas Data Center Campus.
Financial structure
Inherited from campus Meta Los Lunas Data Center Campus.
- Meta AI-dedicated expansion (two buildings)
- $800M. About three-year construction timeline journalist report
- 2025 AI-dedicated expansion (2 buildings)
- $800M journalist report
- Cumulative investment in eight campus buildings
- $2B. ~$2B invested to date across eight buildings tracker
Investment, workforce and specs
Inherited from campus Meta Los Lunas Data Center Campus.
Power
Inherited from campus Meta Los Lunas Data Center Campus. Live grid demand and drought overlay only render on the campus page.
- Power source
- mixed
- Grid operator
- WECC
- Interconnection
- Water
- New AI-dedicated buildings designed to use substantially less water than earlier buildings
Meta New Mexico renewable procurement, 0.89 GW solar, Energized. More than 885 MW of renewable capacity procured in New Mexico to offset campus use
Contracted solar + wind portfolio (~885MW) for Meta Los Lunas, 0.89 GW solar, Financed. ~885MW contracted solar/wind capacity powering the campus
PNM hybrid battery energy storage (BESS) offtake, 0.10 GW storage, Announced. ~100MW battery storage; PNM sought PRC approval of hybrid BESS offtake to serve Meta
Facility record
On the data center map
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
- record: Meta Los Lunas Campus (reported) · source
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Sep 2026Current: operating
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Meta Los Lunas Campus?
Who operates Meta Los Lunas Campus?
Is Meta Los Lunas Campus operating?
How verified is the data on Meta Los Lunas Campus?
Deploy Watch
Track Meta Los Lunas Campus on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Meta Los Lunas Campus: data center facility record. Retrieved September 2, 2026, from https://registry.deploy.report/datacenters/facilities/meta-los-lunas-campus-nm
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/meta-los-lunas-campus-nm.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/meta-los-lunas-campus-nm