Data center campus
BDx CGK4 AI Data Center Park (West Java)
BDx CGK4 AI Data Center Park is an AI data center campus developed by BDx Data Centers in Jatiluhur (Purwakarta). 0.50 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · BDx Data Centers · PT PLN (Persero) · Jatiluhur (Purwakarta), Indonesia
Capacity: announced vs energized
Announced-to-energized gap: 0.50 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Expected online: first half of 2027 (next phase). 7 months away..
| Source | ||||
|---|---|---|---|---|
| Announced | 0.50 GW | 2024-07-31 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Groundbreaking (company-claimed, Sep 2026)
- 640 MW AI campus in Jatiluhur, West Java; 845 MVA PLN grid capacity; built over about three years.
- Building 1 (company-claimed)
- First of six buildings; 120 MW IT in phases; first contracted phase early 2027.
- Cooling (company-claimed)
- Direct-to-chip liquid cooling for up to 500 kW per rack.
- Certification and power (company-claimed)
- NVIDIA DGX-Ready certified Apr 2025; 5 km from Jatiluhur Dam; hydro deal with PJT planned.
- Platform (company-claimed)
- Part of three Indonesia AI campuses with 1.2 GVA+ grid capacity; $320M loan facility in 2026.
- Backer
- I Squared Capital
- IT capacity
- 500 MW at full build; first phase operational
On the data center map
Every tracked data center is on this map, centered on BDx CGK4 AI Data Center Park. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Grid
- PT PLN (Persero) · live in ~4 months
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
The deal
- developer
- BDx Data Centers
- developer
- BDx Indonesia · Colo host/developer (BDx / Indosat / Lintasarta JV).
- operator
- Lintasarta · Runs Deka GPU / GPU Merdeka here.
- grid operator
- PT PLN (Persero) · 30 MVA PPA across CGK3A + CGK4.
- chip supplier
- NVIDIA · H100 SXM (DGX-Ready).
Why here
BDx CGK4 AI Data Center Park is in Jatiluhur (Purwakarta). It connects to the PT PLN (Persero) grid. This siting summary is composed from the record's held fields, not speculation; see methodology.
Timeline
- Nov 2026merged duplicateDuplicate campus record bdx-data-centers-bdx-cgk4-jatiluhur merged into this one (dc-merge-2026-11-18)
- Nov 2026Current: Partially energized
Sources
- BDx Launches First Phase of 500MW Renewable-Powered AI Campus in Indonesia · BDx Data Centers
- Lintasarta Presents GPU Merdeka, powered by NVIDIA · Lintasarta
- BDx Breaks Ground on 640MW AI Data Center in West Java, Backed by 845MVA of Secured Grid Power
- BDx breaks ground on AI data center in West Java; first 120MW building to be ready by early 2027 · W.Media
- BDx CGK4 Jatiluhur — bdx-data-centers facility
720c5a47-de2f-4387-bf19-da401da0655e · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is BDx CGK4 AI Data Center Park (West Java)?
How much power will BDx CGK4 AI Data Center Park (West Java) use?
Who is building BDx CGK4 AI Data Center Park (West Java)?
Is BDx CGK4 AI Data Center Park (West Java) operating yet?
How verified is the data on BDx CGK4 AI Data Center Park (West Java)?
Deploy Watch
Track BDx CGK4 AI Data Center Park (West Java) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). BDx CGK4 AI Data Center Park (West Java): AI data center campus record. Retrieved November 20, 2026, from https://registry.deploy.report/datacenters/bdx-cgk4-ai-data-center-park
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/bdx-cgk4-ai-data-center-park.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/bdx-cgk4-ai-data-center-park
- Data documentation: /data
- Query this programmatically: Deploy MCP